07-30-1973 CCMSPECIAL MEETING
JULY 30, 1973
Mayor Black called the meeting to order at 3:50 P.M. Members present
were Mayor Black, Aldermen Lueneburg, Westlund and Al.rick. Also present
was Administrative Assistant Mealey.
Administrative Assistant Mealey submitted to the Council for review
and authorization Change Order No. 2; Contract No. 402P -Storage Tanks;
Sinking Fund 13; Contractor -Chicago Bridge and Iron at an increase
of $1,450.00 to the original contract.
The equipment and work involves adding a sump pump and drain lines to
each elevated tank to remove the excess ground water present. The
presence of this water was not anticipated during design; if it had
been, the pumps would have been installed in the original contract.
The work will in no way affect the placing of the tanks in service
once the painting is complete. The Contractor will work around the
existing piping. It was City Engineer Priebe's strong recommendation
that this work be approved.
After a brief didcussion Alderman Lueneburg moved that Change Order No. 2
be approved. Alderman Alrick seconded the motion and it was carried.
There being no further business before the Council, meeting was declared
adjourned at 4:00 P.M.