10-26-2022 HUCCPHUTCHINSON UTILITIES COMMISSION
AGENDA
REGULAR MEETING
October 26, 2022
3:00 p.m.
1. CONFLICT OF INTEREST
2. APPROVE CONSENT AGENDA
a. Approve Minutes
b. Ratify Payment of Bills
3. APPROVE FINANCIAL STATEMENTS
4. OPEN FORUM
5. COMMUNICATION
a. City Administrator
b. Divisions
C. Human Resources
d. Legal
e. General Manager
6. POLICIES
a. Review Policies
i. Electric - Rate Schedule
ii. Security Light Rental — Rate to Furnish and Maintain Fixture
iii. Electric Service Requirements & Charges
iv. Temporary Service- Electric
v. Temporary Service in Case of Underground Failure
vi. Electric Meter Placement
vii. Sealing of Meters — Electric
viii. Meter Testing - Electric
ix. Right -of -Way Clearing
x. Tree Removal of Trimming
A. Locating Customer's Underground Utilities — Electric
Ai. Natural Gas — Rate Schedule
xiii. Natural Gas Service Requirements & Charges
xiv. Temporary Service — Natural Gas
xv. Natural Gas Meter Requirements & Placement
xvi. Meter Testing — Natural Gas
xvii. Natural Gas Service Work
xviii. Locating Customer's Underground Utilities — Natural Gas
b. Approve Changes
i. Disconnection of Residential Services by HUC
ii. Disconnection of Commercial Services by HUC
7. UNFINISHED BUSINESS
8. NEW BUSINESS
a. Approve Rollover of Northern Natural Gas Transportation Contract No.
21279
b. Approve 2022 Audit Services with Conway Deuth & Schmiesing
C. Approve Digger Derrick Repair
d. Approve Req#009358 — Design of HCP Interconnect
e. Discussion/Approval of Rescheduling the November 30, 2022 and
December 28, 2022 Regular Commission Meetings if needed
9. ADJOURN
MINUTES
Regular Meeting — Hutchinson Utilities Commission
Wednesday, September 28, 2022
Call to order — 3:00 p.m.
President Matt Cheney called the meeting to order. Members present: President Matt
Cheney; Vice President Anthony Hanson; Secretary Don Martinez; Commissioner Robert
Wendorff; Commissioner Kathy Silvernale; GM Jeremy Carter; Attorney Marc Sebora
1. Conflict of Interest
2. Approve Consent Agenda
a. Approve Minutes
b. Ratify Payment of Bills
Motion by Commissioner Martinez, second by Commissioner Silvernale to Approve
the Consent Agenda. Motion carried unanimously.
3. Approve Financial Statements
Mr. Martig presented the Financial Statements. Electric Division Salaries and
Benefits were up due to accruing some wages back and charged less to work orders.
Operating Expense up by $86K; $50K parts for unit 1 and $35K distribution on
transformers and lines. Watching interest rates; pulled out most of the savings at
Home State Bank and moved it to Citizens Bank which has about a 2% interest rate
difference.
Motion by Commissioner Silvernale, second by Commissioner Hanson to Approve
the Financial Statements. Motion carried unanimously.
4. Open Forum
5. Communication
a. City Administrator— Matthew Jaunich —
1. Early voting has started for the upcoming election which can be done at
the City Center
2. Leaf Vacuuming Service starts Oct 11
3. Wrapping up street projects
4. Provided PD update
b. Divisions
i. Dan Lang, Engineering Services Manager — Nothing to report
ii. Dave Hunstad, Electric Transmission/Distribution Manager — Nothing to
report
iii. Mike Gabrielson, Production Manager — Nothing to report
iv. John Webster, Natural Gas Division Director —
1. Heartland Corn Transmission Line Project Update
v. Jared Martig, Financial Manager — Nothing to report
c. Human Resources — Angie Radke —
i. Continuing to work on 2023 health and dental insurance
d. Legal — Marc Sebora — Nothing to report
e. General Manager — Jeremy Carter
i. Working on 2023 Operating & Capital budget costs — looking at having
preliminary Workshop in November
ii. Missouri River — upgraded bond rating from AA3 to AA2 — refinancing $50M
in debt
iii. MRES Area meeting in Alexandria the last week of October
6. Policies
a. Review Policies
i. After Hours Reconnection Policy
ii. Landlord Acknowledgement
iii. Inserts with Utility Bills
iv. Identity Theft — Red Flag Program
v. MN Government Data Practices Act & Public Records Request
No changes recommended at this time.
b. Approve Changes
i. Travel Expenses — Exempt
ii. Travel Expenses — Non -Exempt
Ms. Radke spoke of the changes to the Travel Expenses Policies to now include
gratuity reimbursement to not exceed 20% of the bill and to be included in the daily
maximum meal allowance.
Motion by Commissioner Hanson, second by Commissioner Martinez to approve the
Policy Changes. Motion carried unanimously.
7. Unfinished Business
8. New Business
a. Approve Req#009328 — City of Hutchinson LED Street Lights 2022
Mr. Hunstad presented Approval of Req#009328 — City of Hutchinson LED Street
Lights 2022. Requisition is for the second year of LED fixtures that are scheduled
for delivery in February.
Motion by Commissioner Hanson, second by Commissioner Wendorff to Approve
Req#009328 — City of Hutchinson LED Street Lights 2022. Motion carried
unanimously.
2
9. Adjourn
There being no further business, a motion by Commissioner Wendorff, second by
Commissioner Silvernale to adjourn the meeting at 3:17p.m. Motion carried
unanimously.
ATTEST:
Matt Cheney, President
3
Don Martinez, Secretary
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 1/26
Amount
Fund: 1 ELECTRIC
09/27/2022
GEN
1194(E)*
ALERUS
HEALTH INSURANCE
401-926-
08
393.00
09/27/2022
GEN
1204(E)
ALERUS
HEALTH INSURANCE MIELKE
401-546-
01
249.
16
09/27/2022
GEN
1220(E)
MISO
Deferred Energy Cost - Miso
174-000-
00
644.53
10/01/2022
GEN
1205(E)*
ARGUS DENTAL
DENTAL INSURANCE -COBRA
242-000-
00
507.81
DENTAL INSURANCE-80o ELEC
242-000-
00
3,778.65
HECK GEN 1205(E) TOTAL FOR FUND 1:
4,286.46
10/04/2022
GEN
1206(E)
ALERUS
HEALTH CARE - B OLSON
242-000-
00
1,213.68
10/04/2022
GEN
1209(E)*
CITIZENS BANK
Office Supplies
401-921-
08
75.13
Office Supplies
401-921-
08
0.02
HECK GEN 1209(E) TOTAL FOR FUND 1:
75.15
10/04/2022
GEN
1221(E)
MISO
Deferred Energy Cost - Miso
174-000-
00
820.33
10/05/2022
GEN
77484*4
ACE HARDWARE
Sales Tax Receivable - Replace
186-000-
00
0.61
Accessory Plant - Materials
402-554-
01
8.88
Grounds - Materials
401-935-
08
4.27
HECK GEN 77484 TOTAL FOR FUND 1:
13.76
10/05/2022
GEN
77485*
ADRIA DAY OR ROBERT VERRIER
DEP REFUND/APPLIED
235-000-
00
195.00
10/05/2022
GEN
77486
ALBA PAMIAS OR WESLEY ABRAMS
OVERPAYMENTS
142-000-
00
72.
92
10/05/2022
GEN
77487*
ALEX OR NAOMI HOLZER
DEP REFUND/APPLIED
235-000-
00
52.00
10/05/2022
GEN
77488
AMANDA LANGNER
OVERPAYMENTS
142-000-
00
158.35
10/05/2022
GEN
77489*
AMANDA ZAKRZEWSKI
DEP REFUND/APPLIED
235-000-
00
78.00
10/05/2022
GEN
77490
AMBER KOST
OVERPAYMENTS
142-000-
00
252.21
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 2/26
Amount
Fund: 1 ELECTRIC
10/05/2022
GEN
77492*
ANDREW SCHUTZ
DEP REFUND/APPLIED
235-000-
00
58.50
10/05/2022
GEN
774934
ANIXTER INC
Sales Tax Receivable - Replace
186-000-
00
14.71
Tray cable. 18ga/2c.
402-554-
01
213.99
HECK GEN 77493 TOTAL FOR FUND 1:
228.70
10/05/2022
GEN
77494*
ANNA MARQUARDT
DEP REFUND/APPLIED
235-000-
00
162.50
10/05/2022
GEN
77495*
ARCBYT
DEP REFUND/APPLIED
235-000-
00
1,170.00
10/05/2022
GEN
77496
BEN WITT OR JANA WITT
OVERPAYMENTS
142-000-
00
54.21
10/05/2022
GEN
77497*
BENJAMIN LIES
DEP REFUND/APPLIED
235-000-
00
117.00
10/05/2022
GEN
77498*
BOETTCHER, TROY
Cip - Residential
401-916-
07
200.00
10/05/2022
GEN
77499*4
BORDER STATES ELECTRIC SUPPLY
ELL, 1/0, 15KV 1STR-1/OSOL, .70-.91,
154-000-
00
283.50
TERMINAL BLOCK, 3 PLACE, "COVERED" CSB
154-000-
00
249.57
PEDESTAL, SECONDARY, NORDIC PRMC-150-MG
154-000-
00
1,584.81
Sales Tax Receivable - New
186-000-
00
19.49
Sales Tax Receivable - New
186-000-
00
17.15
Sales Tax Receivable - New
186-000-
00
108.96
HECK GEN 77499 TOTAL FOR FUND 1:
2,263.48
10/05/2022
GEN
77500
BRADLEY WILLIAMS
OVERPAYMENTS
142-000-
00
63.09
10/05/2022
GEN
77501*4
BRANDED SOLUTIONS
Tearing Account
186-000-
00
32.88
Tearing Account
186-000-
01
289.66
Uniforms & Laundry
401-550-
01
1,458.68
Tearing Account
186-000-
02
38.48
Uniforms & Laundry
401-588-
02
815.46
Tearing Account
186-000-
03
11.73
Tearing Account
186-000-
06
12.13
Tearing Account
186-000-
08
50.45
Uniforms
401-926-
08
588.08
10/20/2022 07:28 AM CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
User: JMartig CHECK DATE FROM 09/23/2022 - 10/21/2022
DE: Hutchinson Utili
Check Date Bank Check # Payee Description Account Dept
Fund: 1 ELECTRIC
HECK GEN 77501 TOTAL FOR FUND
1:
10/05/2022
GEN
77502*
BRENDA PARSLEY
DEP REFUND/APPLIED
235-000-
00
10/05/2022
GEN
77504
CHAD PAEHLKE
OVERPAYMENTS
142-000-
00
10/05/2022
GEN
77505*
CHERYL OR GARY REYNOLDS
DEP REFUND/APPLIED
235-000-
00
10/05/2022
GEN
77507*4
CINTAS CORPORATION 4470
Uniforms & Laundry
401-550-
01
Uniforms & Laundry
401-550-
01
UNIFORMS & LAUNDRY
401-588-
02
UNIFORMS & LAUNDRY
401-588-
02
HECK GEN 77507 TOTAL FOR FUND
1:
10/05/2022
GEN
77508*4
COUNTY OF MCLEOD
Street Lighting & Signal Syste
107-373-
00
10/05/2022
GEN
77509
CULLIGAN ULTRAPURE OF NORTHFIELD
VALVE, 1070155 (K521-X210-1400
LIMIT
154-000-
00
VALVE, 1070155 (K521-X210-1400
LIMIT
154-000-
00
VALVE, 1070154 (K521-X200-1400
154-000-
00
VALVE, 1070154 (K521-X200-1400
154-000-
00
PLATE, LOWER DIAPHRAGM, 443043
154-000-
00
PLATE, LOWER DIAPHRAGM, 443043
154-000-
00
KIT, REPAIR, 1070274
154-000-
00
KIT, REPAIR, 1070274
154-000-
00
HECK GEN 77509 TOTAL FOR FUND
1:
10/05/2022
GEN
77510*
DEREK ALTER
DEP REFUND/APPLIED
235-000-
00
10/05/2022
GEN
77511
DGR ENGINEERING
Electric Distribution System Study
402-592-
02
10/05/2022
GEN
77512
DUVAL, DAN
Cip - Residential
401-916-
07
10/05/2022
GEN
77513
E2 ELECTRICAL SERVICES INC
UNDERGROUND CONDUCTOR
107-367-
00
10/05/2022
GEN
77514
EMALIA BLOMQUIST
OVERPAYMENTS
142-000-
00
Page 3/26
Amount
3,297.55
55.25
135.89
188.50
487.83
542.68
288.08
206.25
372.88
12.16
156.16
5.09
35.40
1.15
272.20
110.50
2,050.00
1,200.00
815.42
46.43
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
Fund: 1 ELECTRIC
10/05/2022
GEN
77515
ERIC HANLEY
10/05/2022
GEN
77516
EVAN STARK OR SHARON STARK
10/05/2022
GEN
77517*
FERGUSON, WALTER
10/05/2022
GEN
775184
FS3 INC
10/05/2022
GEN
77519
GAG SHEET METAL
10/05/2022
GEN
77520*
GORANOWSKI, GALEN
10/05/2022
GEN
77521
GREAT RIVER ENERGY
10/05/2022
GEN
77523*
HANNAH HEARSHMAN
10/05/2022
GEN
77524
HANSON, DAVID
10/05/2022
GEN
77525
HDR ENGINEERING INC
10/05/2022
GEN
77526
HILLYARD/HUTCHINSON
10/05/2022
GEN
775274
HOFFMAN FILTER SERVICE
10/05/2022
GEN
77530*
JACOB POPP OR LILLAN THOMPSON
10/05/2022
GEN
77531*
JEDEDIA NELSON
10/05/2022
GEN
77532
JOHN FORCIER
Account Dept
OVERPAYMENTS
142-000-
00
OVERPAYMENTS
142-000-
00
Cip - Residential
401-916-
07
BATTERY PACK, DRILL HEAD, SIZE
C, 2
154-000-
00
Sales Tax Receivable - New
186-000-
00
Soft Cutting Jaw EK425
401-581-
02
Materials
401-588-
02
HECK GEN 77518 TOTAL FOR FUND
1:
OVERPAYMENTS
142-000-
00
Cip - Residential
401-916-
07
TRANSMISSION EXPENSE
401-565-
03
DEP REFUND/APPLIED
235-000-
00
Cip - Residential
401-916-
07
Generator 41 Outside Services
402-554-
01
Supplies
401-550-
01
PAD, OIL ABSORBANT, 16" X 18",
IN WPHL,
154-000-
00
SALES TAX
401-588-
02
HECK GEN 77527 TOTAL FOR FUND
1:
DEP REFUND/APPLIED
235-000-
00
DEP REFUND/APPLIED
235-000-
00
OVERPAYMENTS
142-000-
00
Page 4/26
Amount
43.89
20.85
200.00
76.00
5.81
1,302.68
95.42
25.00
220,643.39
48.75
25.00
2,122.IS
93.68
111.50
110.50
97.50
71.59
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 5/26
Amount
Fund: 1 ELECTRIC
10/05/2022
GEN
77533*
JOSEPH ANDRUS
DEP REFUND/APPLIED
235-000-
00
65.00
10/05/2022
GEN
77534*
JUNIOR HENRIQUEZ
DEP REFUND/APPLIED
235-000-
00
201.50
10/05/2022
GEN
77535*
KATHRYN COBBETT
DEP REFUND/APPLIED
235-000-
00
42.25
10/05/2022
GEN
77536*
KEN KRUSSOW
DEP REFUND/APPLIED
235-000-
00
201.50
10/05/2022
GEN
77537*
KEN KRUSSOW OR CYNTHIA NOBLES
DEP REFUND/APPLIED
235-000-
00
195.00
10/05/2022
GEN
77538*
KEVIN PLAMANN
DEP REFUND/APPLIED
235-000-
00
182.00
10/05/2022
GEN
77539*
KRISTIE SCHLANGEN
DEP REFUND/APPLIED
235-000-
00
247.00
10/05/2022
GEN
775404
KURITA AMERICA INC
8808 DESCALING ACID
154-000-
00
1,414.93
FREIGHT
401-588-
02
112.40
SALES TAX
401-588-
02
105.10
HECK GEN 77540 TOTAL FOR FUND 1:
1,632.43
10/05/2022
GEN
77541*
KYLE OCH
DEP REFUND/APPLIED
235-000-
00
146.25
10/05/2022
GEN
77542*
LINDA NICOLAY
DEP REFUND/APPLIED
235-000-
00
107.25
10/05/2022
GEN
77543*
LIZBETH MEDINA
DEP REFUND/APPLIED
235-000-
00
91.00
10/05/2022
GEN
77545
LUBE-TECH & PARTNERS, LLC
OIL, MOBIL PEGASUS 1005
154-000-
00
7,878.16
10/05/2022
GEN
77546*
MARCO TECHNOLOGIES, LLC
OFFICE SUPPLIES
401-921-
08
0.94
10/05/2022
GEN
775474
MATHESON TRI-GAS INC
Sales Tax Receivable - Replace
186-000-
00
9.45
Generator 41 Material
402-554-
01
137.43
HECK GEN 77547 TOTAL FOR FUND 1:
146.88
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 6/26
Amount
Fund: 1 ELECTRIC
10/05/2022
GEN
77548
MCALLISTER, PAUL
Cip - Residential
401-916-
07
1,200.00
10/05/2022
GEN
775494
MCC ENERGY SOLUTIONS, LLC
I AM MANAGEMENT FEES
401-555-
02
3,900.00
IAM USAGE FEES
401-556-
03
3,050.00
CHECK GEN 77549 TOTAL FOR FUND 1:
6,950.00
10/05/2022
GEN
77550*
MCKITTRICK, DEBRA
Cip - Residential
401-916-
07
25.00
Cip - Residential
401-916-
07
200.00
HECK GEN 77550 TOTAL FOR FUND 1:
225.00
10/05/2022
GEN
77551
MIDLAND MORTGAGE OR JASON KEEBLE
OVERPAYMENTS
142-000-
00
84.
72
10/05/2022
GEN
77552*
MILTON OR JOANNE JOHNSON
DEP REFUND/APPLIED
235-000-
00
120.25
10/05/2022
GEN
77553*
MONA DINNING
DEP REFUND/APPLIED
235-000-
00
214.50
10/05/2022
GEN
77554
MYA GOSSE
OVERPAYMENTS
142-000-
00
2.01
10/05/2022
GEN
77556*
NICOLE PATOCK
DEP REFUND/APPLIED
235-000-
00
162.50
10/05/2022
GEN
77557*
NIELSEN, PAUL
Cip - Residential
401-916-
07
200.00
10/05/2022
GEN
77558*4
NORTHERN STATES SUPPLY INC
Supplies
401-550-
01
26.52
Line - Materials
401-581-
02
26.50
HECK GEN 77558 TOTAL FOR FUND 1:
53.02
10/05/2022
GEN
77559*
NYLA OR MERLIN EGGERSGLUESS
DEP REFUND/APPLIED
235-000-
00
130.00
10/05/2022
GEN
77560*4
OXYGEN SERVICE COMPANY INC
Maintenance Other - Materials
402-554-
01
55.00
10/05/2022
GEN
77562*4
PRO AUTO & TRANSMISSION REPAIR
Vehicle/Equipment Fuel
401-550-
01
73.46
Vehicle/Equipment Fuel
401-550-
01
71.83
HECK GEN 77562 TOTAL FOR FUND 1:
145.29
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 7/26
Amount
Fund: 1 ELECTRIC
10/05/2022
GEN
77565
RICHARD C THOMPSON OR DOUG
OVERPAYMENTS
142-000-
00
2,213.
02
10/05/2022
GEN
77567
RUSSELL, JANNA
Cip - Residential
401-916-
07
25.00
10/05/2022
GEN
77568*
SARA YOUNG
DEP REFUND/APPLIED
235-000-
00
286.00
10/05/2022
GEN
77569*
SHANNON KLING
DEP REFUND/APPLIED
235-000-
00
39.00
10/05/2022
GEN
77570
SHAWN ANDERSON
OVERPAYMENTS
142-000-
00
44.63
10/05/2022
GEN
77571*
SHRED RIGHT
OFFICE SUPPLIES -SHREDDING SERVICES
401-921-
08
13.76
10/05/2022
GEN
77572*
SKYLAR BENSON
DEP REFUND/APPLIED
235-000-
00
156.00
10/05/2022
GEN
77573
STEVE FIECKE
OVERPAYMENTS
142-000-
00
23.57
10/05/2022
GEN
77574*
STEVEN UNLIMITED
DEP REFUND/APPLIED
235-000-
00
357.50
10/05/2022
GEN
77575*
SUSAN STUPCA
DEP REFUND/APPLIED
235-000-
00
39.00
10/05/2022
GEN
77576*
TOTAL COMPLIANCE SOLUTIONS INC
DRUG/HEARING TESTING SERVICES
401-923-
08
5,625.00
10/05/2022
GEN
77577*
UIS/SOURCECORP
COLLECTION - MATERIALS
401-903-
06
1,935.20
10/05/2022
GEN
77578*
UNDREENIKIA CAPPELEN
DEP REFUND/APPLIED
235-000-
00
78.00
10/05/2022
GEN
77579*
UNITED PARCEL SERVICE
MAIL SERVICES - UPS, FEDEX
401-921-
08
62.32
10/05/2022
GEN
77580*
VIDEOTRONIX INC
Grounds - Outside Services
401-935-
08
339.63
10/05/2022
GEN
77581
VIKING ELECTRIC
SWITCH, SIMATIC NET SCALANCE X212-2
154-000-
00
6,758.98
SWITCH, DEV-TRANS-ETHERNET, 4- PORT,
154-000-
00
1,846.15
HECK GEN 77581 TOTAL FOR FUND 1:
8,605.13
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 8/26
Amount
Fund: 1 ELECTRIC
10/05/2022
GEN
775824
WARTSILA OF NORTH AMERICA, INC
SENSOR, PRESSURE, 4516 541
154-000-
00
5,541.30
Sales Tax Receivable - Replace
186-000-
00
58.22
FREIGHT
401-588-
02
280.91
HECK GEN 77582 TOTAL FOR FUND 1:
5,880.43
10/05/2022
GEN
77583*
WILLIAM OR KATHRYN WATTS
DEP REFUND/APPLIED
235-000-
00
273.00
10/05/2022
GEN
77584*
YRC FREIGHT
MAIL SERVICES - UPS, FEDEX
401-921-
08
164.60
10/06/2022
GEN
1217(E)*
INVOICE CLOUD
collection - Materials
401-903-
06
1,801.25
10/11/2022
GEN
1222(E)
MISO
Deferred Energy Cost - Miso
174-000-
00
29,175.20
10/11/2022
GEN
1223(E)
MISO
Deferred Energy Cost - Miso
174-000-
00
848.72
10/14/2022
GEN
1214(E)
MISO
SCHEDULE 10
401-565-
03
5,507.99
10/14/2022
GEN
1215(E)
MISO
26
401-565-
03
21,964.61
26A
401-565-
03
28,505.33
26E
401-565-
03
1.68
HECK GEN 1215(E) TOTAL FOR FUND 1:
50,471.62
10/14/2022
GEN
1216(E)
MISO
2
401-565-
03
16,447.61
Transmission Expense
401-565-
03
5,647.71
HECK GEN 1216(E) TOTAL FOR FUND 1:
22,095.32
10/18/2022
GEN
1224(E)
MISO
Deferred Energy Cost - Miso
174-000-
00
789.93
10/19/2022
GEN
77585*
A & K REPAIR, INC
Grounds - Materials
401-935-
08
180.70
10/19/2022
GEN
77586*4
ACE HARDWARE
Station Equipment (Switchgear,
107-362-
00
24.53
Station Equipment (Switchgear,
107-362-
00
14.95
Station Equipment (Switchgear,
107-362-
00
0.51
Generator 41 Aux Boiler
401-547-
01
106.86
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
Fund: 1 ELECTRIC
10/19/2022 GEN 775874 ANIXTER INC
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
10/19/2022 GEN 77588 ASH, MATTHEW
10/19/2022 GEN 77590*4 BORDER STATES ELECTRIC SUPPLY
Page 9/26
Account Dept
Amount
Supplies
401-550-
01
18.36
Supplies
401-550-
01
10.68
Generator 41 Material
402-554-
01
11.31
Accessory Plant - Materials
402-554-
01
19.23
Maintenance Other - Materials
402-554-
01
11.75
HECK GEN 77586 TOTAL FOR FUND 1:
218.18
SIS wire
107-362-
00
702.90
Burndy ring connectors
107-362-
00
1,075.00
Sales Tax Receivable - Replace
186-000-
00
61.25
Sales Tax Receivable - Replace
186-000-
00
76.21
FREIGHT
401-588-
02
188.00
FREIGHT
401-588-
02
33.48
HECK GEN 77587 TOTAL FOR FUND 1:
2,136.84
Cip - Residential
401-916-
07
50.00
CONDUCTOR, 350 MCM 600V URD TRIPLEX
154-000-
00
11,500.00
TAPE, RED, 3/4" x 66, 3M SCOTCH 35
154-000-
00
50.40
GREASE, LUBRICATING, SILICONE
154-000-
00
26.
94
TAPE, ORANGE, 3/4" x 66, 3M SCOTCH 35
154-000-
00
10.08
CONNECTOR, MULTI TAP STUD WITH COVER,
154-000-
00
957.24
BUSHING, WELL INSERT, FEED THRU 200A
154-000-
00
274.94
DISPENSER, TAPE, SLW WRITE -ON WITH SMP
154-000-
00
89.10
TRANS GROUND LUG GC 207 1/0 HUBBELL
154-000-
00
101.75
JUNCTION BOX, 1 PH, 30 X 30 X 18, SEC
154-000-
00
666.59
TAPE, BLUE, 3/4" x 66, 3M SCOTCH
154-000-
00
50.40
SHOVEL, 42, CLOSED BACK 48",
154-000-
00
176.65
Sales Tax Receivable - New
186-000-
00
790.70
Sales Tax Receivable - New
186-000-
00
45.83
Sales Tax Receivable - New
186-000-
00
15.61
Sales Tax Receivable - Replace
186-000-
00
103.83
Materials
401-588-
02
1.10
BATTERY, SIZE 9V
401-588-
02
18.24
HECK GEN 77590 TOTAL FOR FUND 1:
14,879.40
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
Fund: 1 ELECTRIC
10/19/2022 GEN 775934 CENTRAL HYDRAULICS
10/19/2022 GEN 77595 CHAS J BURICH
10/19/2022 GEN 77596*4 CINTAS CORPORATION 4470
10/19/2022 GEN 77597*4 CITY OF HUTCHINSON
Account Dept
Page 10/26
Amount
O-RING, HYD STARTER HOSES, 568-219V
154-000-
00
17.34
O-RING, HOSE CONNECTION END, 568-222V
154-000-
00
20.16
O-RING, HOSE CONNECTION END, 568-225V
154-000-
00
25.50
Sales Tax Receivable - New
186-000-
00
5.21
Supplies
401-550-
01
49.69
FREIGHT
401-588-
02
12.74
HECK GEN 77593 TOTAL FOR FUND 1:
130.64
OVERPAYMENTS
142-000-
00
56. 12
Uniforms & Laundry
401-550-
01
475.99
Uniforms & Laundry
401-550-
01
619.96
Uniforms & Laundry
401-550-
01
453.32
UNIFORMS & LAUNDRY
401-588-
02
395.42
UNIFORMS & LAUNDRY
401-588-
02
318.89
UNIFORMS & LAUNDRY
401-588-
02
299. 05
HECK GEN 77596 TOTAL FOR FUND 1: 2,562.63
Accounts Payable To City Of Hu
234-000-
00
323,385.75
Generator 41 Water & Sewer
401-547-
01
975.73
Generator 41 Water & Sewer
401-547-
01
763.75
Waste Disposal
401-550-
01
3,125.06
Waste Disposal
401-550-
01
48.84
Waste Disposal
401-550-
01
527.53
VEHICLE/EQUIPMENT FUEL -POWER
401-550-
01
337.44
VEHICLES/EQUIPMENT FUEL-ELEC
401-588-
02
1,124.22
Line - Materials
402-594-
02
8.66
Vehicles - Material
402-598-
02
25.00
IT ADMIN AND SUPPORT 75/25
401-921-
08
19, 769. 43
IT ADMIN AND SUPPORT 75/25
401-921-
08
15,559.86
LEGAL SERVICES 75/25
401-923-
08
7,875.00
HUMAN RESOURCES SERVICES 75/25
401-923-
08
6,201.56
Utility Expenses - Water/Waste
401-930-
08
14.70
Utility Expenses - Water/Waste
401-930-
08
499.02
VEHICLES/EQUIPMENT FUEL-ADMIN 55/45
401-935-
08
39.52
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 11/26
Amount
Fund: 1 ELECTRIC
HECK GEN 77597 TOTAL FOR FUND 1:
380,281.07
10/19/2022
GEN
77598
CORE & MAIN
Meters (Boxes)
107-370-
00
80.00
10/19/2022
GEN
77599
CREEKSIDE SOILS
Materials
401-588-
02
59.32
10/19/2022
GEN
77600*
DEMING, CORY
Cip - Residential
401-916-
07
27.00
10/19/2022
GEN
77601*
BRACT, JENNIFER
Cip - Residential
401-916-
07
25.00
10/19/2022
GEN
77602
FASTENAL COMPANY
Station Equipment (Switchgear,
107-362-
00
8.96
Station Equipment (Switchgear,
107-362-
00
8.30
HECK GEN 77602 TOTAL FOR FUND 1:
17.26
10/19/2022
GEN
77603
FS3 INC
Materials
401-588-
02
253.88
10/19/2022
GEN
77604*4
GOPHER STATE ONE -CALL INC
Line - Materials
401-581-
02
185.63
10/19/2022
GEN
77605
HER ENGINEERING INC
Plant 1 Pipe Demo Plan Engineering
402-554-
01
3,345.30
Outside Services
402-554-
01
7.50
HECK GEN 77605 TOTAL FOR FUND 1:
3,352.80
10/19/2022
GEN
77606*4
HILLYARD/HUTCHINSON
Supplies
401-550-
01
361.23
10/19/2022
GEN
77607*
HUTCHFIELD SERVICES INC
Grounds - Outside Services
401-935-
08
1,093.21
10/19/2022
GEN
77608*4
HUTCHINSON CO-OP
Vehicles - Material
402-598-
02
761.38
Power Equipment - Materials
402-598-
02
17.88
HECK GEN 77608 TOTAL FOR FUND 1:
779.26
10/19/2022
GEN
77609*4
HUTCHINSON LEADER
Cip - Marketing
401-916-
07
242.25
10/19/2022
GEN
77610*4
HUTCHINSON WHOLESALE SUPPLY CO
Vehicles - Material
402-598-
02
104.72
Power Equipment - Materials
402-598-
02
24.31
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
Fund: 1 ELECTRIC
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
10/19/2022 GEN 77611 IEM ENERGY CONSULTANTS
10/19/2022 GEN 77612* INNOVATIVE OFFICE SOLUTIONS
10/19/2022 GEN 77613* JLR GARAGE DOOR SERVICE INC
10/19/2022 GEN 77615 KRECH OJARD & ASSOCIATES INC
10/19/2022 GEN 77616 KURITA AMERICA INC
10/19/2022 GEN 77617 LANDSKAPINGS
10/19/2022 GEN 77618 LEAGUE OF MINNESOTA CITIES
10/19/2022 GEN 77619 LILLIAN FRIENDT
Account Dept
Page 12/26
Amount
Grounds - Materials
401-935-
08
48.60
HECK GEN 77610 TOTAL FOR FUND 1:
177.63
Development of RFP LM6000
402-554-
01
4,515.00
Generator 41 Outside Services
402-554-
01
15.00
U9 retaining ring testing and Gen Test
402-554-
01
643.62
Generator 49 Labor
402-554-
01
1.38
HECK GEN 77611 TOTAL FOR FUND 1:
5,175.00
Office Supplies
401-921-
08
197.81
Office Supplies
401-921-
08
19.24
Office Supplies
401-921-
08
13.23
HECK GEN 77612 TOTAL FOR FUND 1:
230.28
Grounds - Materials
401-935-
08
82.50
Grounds - Materials
401-935-
08
135.40
HECK GEN 77613 TOTAL FOR FUND 1:
217.90
Engineering Serices for Plant 2
401-546-
01
8,341.50
Engineering - Labor
401-546-
01
2.25
Engineering Serices for Plant 2
401-546-
01
4,183.20
Engineering - Labor
401-546-
01
7.00
Engineering Serices for Plant 2
401-546-
01
8,814.60
Engineering - Labor
401-546-
01
19.15
HECK GEN 77615 TOTAL FOR FUND 1:
21,367.70
CL0142-15, Boil out 881 15 gallon
401-547-
01
1,358.64
Generator 41 Aux Boiler
401-547-
01
0.01
HECK GEN 77616 TOTAL FOR FUND 1:
1,358.65
Underground Conductor
107-367-
00
48.32
WORKERS COMPENSATION
401-546-
01
18.
96
OVERPAYMENTS 142-000- 00 211.86
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 13/26
Amount
Fund: 1 ELECTRIC
10/19/2022
GEN
77622
MCLEOD COUNTY CHIROPRACTIC CTR
HEALTH INSURANCE
401-926-
08
180.00
10/19/2022
GEN
77623*
MEDICA
HEALTH INSURANCE 85% ELEC
242-000-
00
51,143.84
HEALTH INSURANCE -COBRA
242-000-
00
1,918.15
HECK GEN 77623 TOTAL FOR FUND 1:
53,061.99
10/19/2022
GEN
77624*
MN MUNICIPAL UTILITIES ASSOCIATION
MISC SERVICES-QTR SAFETY/MGMT 750
401-923-
08
4, 878.56
DUES/MEMBERSHIP EXPENSE-QTR ELEC DUES
401-930-
08
1,312.50
CHECK GEN 77624 TOTAL FOR FUND 1:
6,191.06
10/19/2022
GEN
77627*
NUVERA
TELEPHONE
401-921-
08
1,967.93
10/19/2022
GEN
77628*4
OXYGEN SERVICE COMPANY INC
Maintenance Other - Materials
402-554-
01
87.26
Maintenance Other - Materials
402-554-
01
72.78
HECK GEN 77628 TOTAL FOR FUND 1:
160.04
10/19/2022
GEN
776294
PETTY CASH
Training - Expense
401-580-
02
10.45
Training - Expense
401-580-
02
21.17
Training - Expense
401-580-
02
23.00
Training - Expense
401-580-
02
22.17
Line - Materials
402-594-
02
28.54
Line - Materials
402-594-
02
14.64
Dues/Membership Expense
401-930-
08
20.00
HECK GEN 77629 TOTAL FOR FUND 1:
139.97
10/19/2022
GEN
776304
POWMAT LTD.
THERMOCOUPLE, EXHAUST T/C EXTENDED 9'
154-000-
00
770.00
FREIGHT
401-588-
02
41.90
HECK GEN 77630 TOTAL FOR FUND 1:
811.90
10/19/2022
GEN
77631*
PREMIUM WATERS INC
OFFICE SUPPLIES -BOTTLED WATER
401-921-
08
19.
88
10/19/2022
GEN
77632*4
QUADE ELECTRIC
Station Equipment (Switchgear,
107-362-
00
139.47
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
Fund: 1 ELECTRIC
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
10/19/2022 GEN 77633* QUADIENT-LEASE
10/19/2022 GEN 77634 RDO EQUIPMENT
10/19/2022 GEN 77637 TERRI SCHNABEL
10/19/2022 GEN 77638 TK ELEVATOR CORPORATION
10/19/2022 GEN 77639 TWO-WAY COMMUNICATIONS INC
10/19/2022 GEN 77640*4 VERIZON WIRELESS
10/19/2022 GEN 776414 WESCO RECEIVABLES CORP
10/19/2022 GEN 77642*4 WEST CENTRAL SANITATION INC
10/19/2022 GEN 77643 WILD FLOWER PROPERTIES
Account Dept
Station Equipment (Switchgear,
107-362-
00
HECK GEN 77632 TOTAL FOR FUND 1:
LEASE/SERVICE AGREEMENTS
401-921-
08
LEASE/SERVICE AGREEMENTS
401-921-
08
HECK GEN 77633 TOTAL FOR FUND 1:
Power Equipment - Materials
402-598-
02
Power Equipment - Materials
402-598-
02
HECK GEN 77634 TOTAL FOR FUND 1:
OVERPAYMENTS
142-000-
00
Accessory Plant - Labor
402-554-
01
Telephone
401-921-
08
TELEPHONE
401-921-
08
BASEMENT, (GROUND SLEEVE), 3 PH JOT
154-000-
00
Sales Tax Receivable - New
186-000-
00
FREIGHT
401-588-
02
HECK GEN 77641 TOTAL FOR FUND 1:
GENERATOR 41 WATER & SEWER -INDUSTRIAL
401-547-
01
WASTE DISPOSAL-4TH AVE
401-550-
01
UTILITY ESP - WATER/WASTE 55/45-
401-930-
08
HECK GEN 77642 TOTAL FOR FUND 1:
OVERPAYMENTS
142-000-
00
OVERPAYMENTS
142-000-
00
OVERPAYMENTS
142-000-
00
HECK GEN 77643 TOTAL FOR FUND 1:
Page 14/26
Amount
64.12
203.59
355.82
654.30
1,010.12
1,010.74
786.16
1,796.90
36.14
36,490.60
829.30
1,030.36
2,080.00
164.93
114.56
184.95
498.52
567.97
1,689.22
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 15/26
Amount
Fund: 1 ELECTRIC
10/19/2022
GEN
776444
ZIEGLER POWER SYSTEMS EXTENSION-SPARKPLUG
154-000-
00
587.50
RELAY/SOLENOID, STARTER MAO 0401980
154-000-
00
235.00
SENSOR, NOX - POSITION 220
154-000-
00
2,137.50
FREIGHT
401-588-
02
38.76
FREIGHT
401-588-
02
12.63
HECK GEN 77644 TOTAL FOR FUND 1:
3,011.39
10/20/2022
GEN
1211(E)*4
BP CANANDA ENERGY SOLUTIONS GENERATOR 41 NATURAL GAS
401-547-
01
178,772.73
GENERATOR 41 NATURAL GAS
401-547-
01
181.70
GENERATOR 45 NATURAL GAS
401-547-
01
46, 689.
72
GENERATOR 45 NATURAL GAS
401-547-
01
27.
95
GENERATOR 46 NATURAL GAS
401-547-
01
76, 056.31
GENERATOR 46 NATURAL GAS
401-547-
01
34.07
Generator 47 Natural Gas
401-547-
01
78,067.30
Generator 47 Natural Gas
401-547-
01
34.07
Generator 49 Natural Gas
401-547-
01
87.36
Utility Expenses - Water/Waste
401-930-
08
57.50
HECK GEN 1211(E) TOTAL FOR FUND 1:
380,008.71
10/21/2022
GEN
1213(E)
MRES Purchased Power
401-555-
02
808,359.95
Total for fund 1 ELECTRIC
2,142,208.90
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 16/26
Amount
Fund: 2 GAS
09/27/2022
GEN
1194(E)*
ALERUS
HEALTH INSURANCE
401-926-
08
131.00
10/01/2022
GEN
1205(E)*
ARGUS DENTAL
DENTAL INSURANCE-20o GAS
242-000-
00
944.67
10/04/2022
GEN
1209(E)*
CITIZENS BANK
Office Supplies
401-921-
08
75.12
Office Supplies
401-921-
08
0.01
HECK GEN 1209(E) TOTAL FOR FUND 2:
75.13
10/05/2022
GEN
77484*4
ACE HARDWARE
Services
107-380-
00
15.35
Materials
401-874-
04
8.30
Materials
401-874-
04
55.12
Materials
401-874-
04
7.05
Materials
402-892-
04
27.70
Materials
402-892-
04
1.69
Grounds - Materials
401-935-
08
4.27
Grounds - Materials
401-935-
08
1.06
HECK GEN 77484 TOTAL FOR FUND 2:
120.54
10/05/2022
GEN
77485*
ADRIA DAY OR ROBERT VERRIER
DEP REFUND/APPLIED
235-000-
00
105.00
10/05/2022
GEN
77487*
ALEX OR NAOMI HOLZER
DEP REFUND/APPLIED
235-000-
00
28.00
10/05/2022
GEN
77489*
AMANDA ZAKRZEWSKI
DEP REFUND/APPLIED
235-000-
00
42.00
10/05/2022
GEN
77491
AMERICAN PUBLIC GAS ASSOCIATION
DUES/MEMBERSHIP EXPENSE
401-930-
08
5,214.51
10/05/2022
GEN
77492*
ANDREW SCHUTZ
DEP REFUND/APPLIED
235-000-
00
31.50
10/05/2022
GEN
77494*
ANNA MARQUARDT
DEP REFUND/APPLIED
235-000-
00
87.50
10/05/2022
GEN
77495*
ARCBYT
DEP REFUND/APPLIED
235-000-
00
630.00
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
Fund: 2 GAS
10/05/2022 GEN 77497* BENJAMIN LIES
10/05/2022 GEN 77498* BOETTCHER, TROY
10/05/2022 GEN 77499*4 BORDER STATES ELECTRIC SUPPLY
10/05/2022 GEN 77501*4 BRANDED SOLUTIONS
10/05/2022 GEN 77502* BRENDA PARSLEY
10/05/2022 GEN 77503 CENTRAL MCGOWAN
10/05/2022 GEN 77505* CHERYL OR GARY REYNOLDS
Account Dept
Page 17/26
Amount
DEP REFUND/APPLIED
235-000-
00
63.00
Cip - Residential
401-916-
07
350.00
REDUCER, SWAGE, 2" X 3/4", STD, BLE X
154-000-
00
117.58
VALVE, METER, 1", INS, LOCKWING, PLG
154-000-
00
270. 52
BRACKET, WALL MT RISER, 3/4", REFER TO
154-000-
00
403.40
NIPPLE, 2" X 6", BM, STD, SMLS, TEE
154-000-
00
24.12
THREAD-O-LET, 1/4" X 2 1/2" X 1 1/4",
154-000-
00
85.40
TEE, WELD FITTING, STRAIGHT, 2", SMLS,
154-000-
00
73.18
ELL, WELD FITTING, 90 DEG, 2", SMLS,
154-000-
00
30. 82
CAP, 2", SMLS WELD FITTING , STD WGHT
154-000-
00
104.56
REDUCER, SWAGE, 2" X 1", STD, BLE X ISE
154-000-
00
40.27
SALES TAX
401-874-
04
8.08
SALES TAX
401-874-
04
46.33
SALES TAX
401-874-
04
7.53
Materials
401-874-
04
17.12
HECK GEN 77499 TOTAL FOR FUND 2:
1,228.91
Tearing Account
186-000-
00
1.82
CLEARING ACCOUNT
186-000-
04
17.29
Uniforms & Laundry
401-880-
04
598.59
Tearing Account
186-000-
05
4.19
Tearing Account
186-000-
06
9.92
CLEARING ACCOUNT
186-000-
08
16.85
Uniforms
401-926-
08
268.40
HECK GEN 77501 TOTAL FOR FUND 2:
917.06
DEP REFUND/APPLIED
235-000-
00
29.75
Other Equipment - Materials
402-895-
04
261.08
DEP REFUND/APPLIED
235-000-
00
101.50
10/20/2022 07:28 AM CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
User: JMartig CHECK DATE FROM 09/23/2022 - 10/21/2022
DE: Hutchinson Utili
Check Date Bank Check # Payee Description Account Dept
Fund: 2 GAS
10/05/2022
GEN
775064
CHICAGO TUBE AND IRON
PIPE, 2", ELK STEEL, BARE,
API-5L,
154-000-
00
PIPE, 4", STD ELK CS ERW,
A53 GR B, 20
154-000-
00
PIPE, 3", STD ELK CS ERW,
A53 GRB,
154-000-
00
ENERGY SURCHARGE
401-874-
04
HECK GEN 77506 TOTAL FOR
FUND 2:
10/05/2022
GEN
77507*4
CINTAS CORPORATION 4470
UNIFORMS & LAUNDRY
401-880-
04
UNIFORMS & LAUNDRY
401-880-
04
HECK GEN 77507 TOTAL FOR
FUND 2:
10/05/2022
GEN
77508*4
COUNTY OF MCLEOD
Materials
402-892-
04
10/05/2022
GEN
77510*
DEREK ALTER
DEP REFUND/APPLIED
235-000-
00
10/05/2022
GEN
77517*
FERGUSON, WALTER
Cip - Residential
401-916-
07
10/05/2022
GEN
77520*
GORANOWSKI, GALEN
Cip - Residential
401-916-
07
10/05/2022
GEN
77522
GROEBNER & ASSOCIATES INC
Sensus P/N# 143-16-023-01
3/4" Brass
402-892-
04
Sensus P/N# 143-16-021-04
5"- 8 1/2"
402-892-
04
FREIGHT & TAXES
402-892-
04
HECK GEN 77522 TOTAL FOR
FUND 2:
10/05/2022
GEN
77523*
HANNAH HEARSHMAN
DEP REFUND/APPLIED
235-000-
00
10/05/2022
GEN
77528
HUTCHINSON WHOLESALE SUPPLY CO
Materials
401-874-
04
Vehicles - Material
402-895-
04
HECK GEN 77528 TOTAL FOR
FUND 2:
10/05/2022
GEN
775294
IDEAL SHIELD
BUMPER POST SHIELD, 1/8" WALL
154-000-
00
BUMPER POST SHIELD, 1/8" WALL
154-000-
00
FREIGHT & SALES TAX
401-874-
04
Page 18/26
Amount
522.65
2,724.88
I,064.26
15.09
4,326.88
147.72
147.72
295.44
294.00
59.50
350.00
50.00
96.42
22.24
26.25
57.69
459.90
329.90
101.27
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
Fund: 2 GAS
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
10/05/2022
GEN
77530*
JACOB POPP OR LILLAN THOMPSON
10/05/2022
GEN
77531*
JEDEDIA NELSON
10/05/2022
GEN
77533*
JOSEPH ANDRUS
10/05/2022
GEN
77534*
JUNIOR HENRIQUEZ
10/05/2022
GEN
77535*
KATHRYN COBBETT
10/05/2022
GEN
77536*
KEN KRUSSOW
10/05/2022
GEN
77537*
KEN KRUSSOW OR CYNTHIA NOBLES
10/05/2022
GEN
77538*
KEVIN PLAMANN
10/05/2022
GEN
77539*
KRISTIE SCHLANGEN
10/05/2022
GEN
77541*
KYLE OCH
10/05/2022
GEN
77542*
LINDA NICOLAY
10/05/2022
GEN
77543*
LIZBETH MEDINA
10/05/2022
GEN
77544
LOCATORS & SUPPLIES INC
Account Dept
Page 19/26
Amount
FREIGHT & SALES TAX
401-874-
04
95.99
HECK GEN 77529 TOTAL FOR FUND 2:
987.06
DEP REFUND/APPLIED
235-000-
00
59.50
DEP REFUND/APPLIED
235-000-
00
52.50
DEP REFUND/APPLIED
235-000-
00
35.00
DEP REFUND/APPLIED
235-000-
00
108.50
DEP REFUND/APPLIED
235-000-
00
22.75
DEP REFUND/APPLIED
235-000-
00
108.50
DEP REFUND/APPLIED
235-000-
00
105.00
DEP REFUND/APPLIED
235-000-
00
98.00
DEP REFUND/APPLIED
235-000-
00
133.00
DEP REFUND/APPLIED
235-000-
00
78.75
DEP REFUND/APPLIED
235-000-
00
57.75
DEP REFUND/APPLIED
235-000-
00
49.00
SAFETY VEST, MLK-FM389Z-3XL
401-880-
04
104.36
RAIN COAT, NASCO, NOMEX 1503JFY, 3XL
401-880-
04
152.50
HECK GEN 77544 TOTAL FOR FUND 2:
256.86
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 20/26
Amount
Fund: 2 GAS
10/05/2022
GEN
77546*
MARCO TECHNOLOGIES, LLC
OFFICE SUPPLIES
401-921-
08
0.31
10/05/2022
GEN
77550*
MCKITTRICK, DEBRA
Cip - Residential
401-916-
07
50.00
Cip - Residential
401-916-
07
350.00
HECK GEN 77550 TOTAL
FOR FUND 2:
400.00
10/05/2022
GEN
77552*
MILTON OR JOANNE JOHNSON
DEP REFUND/APPLIED
235-000-
00
64.75
10/05/2022
GEN
77553*
MONA DINNING
DEP REFUND/APPLIED
235-000-
00
115.50
10/05/2022
GEN
77555
NELSON TECHNOLOGIES INC
Mooney P/N# 103-175-01
3" Single
402-892-
04
2,086.70
Mooney P/N# 102-161-01
2" Large
402-892-
04
220.21
Mooney P/N# 240-004-01
Type 24
402-892-
04
719.00
FREIGHT & SALES TAX
402-892-
04
259.20
HECK GEN 77555 TOTAL
FOR FUND 2:
3,285.11
10/05/2022
GEN
77556*
NICOLE PATOCK
DEP REFUND/APPLIED
235-000-
00
87.50
10/05/2022
GEN
77557*
NIELSEN, PAUL
Cip - Residential
401-916-
07
350.00
10/05/2022
GEN
77558*4
NORTHERN STATES SUPPLY INC
Materials
401-874-
04
100.17
Materials
401-874-
04
26.50
HECK GEN 77558 TOTAL
FOR FUND 2:
126.67
10/05/2022
GEN
77559*
NYLA OR MERLIN EGGERSGLUESS
DEP REFUND/APPLIED
235-000-
00
70.00
10/05/2022
GEN
77560*4
OXYGEN SERVICE COMPANY INC
Materials
401-874-
04
55.54
10/05/2022
GEN
77561
POKORNOWSKI TRUCKING, LLC
Mains
107-367-
00
1,550.00
10/05/2022
GEN
77562*4
PRO AUTO & TRANSMISSION REPAIR
Vehicles - Material
402-895-
04
953.44
10/05/2022
GEN
77563
BATH RACING, INC
Materials
402-892-
04
138.00
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 21/26
Amount
Fund: 2 GAS
10/05/2022
GEN
775644
RHINO MARKING & PROTECTION SYSTEMS
MARKER, YELLOW HYBRID 3-RAIL, 62"
154-000-
00
210.00
FREIGHT
401-874-
04
50.24
HECK GEN 77564 TOTAL FOR FUND 2:
260.24
10/05/2022
GEN
77566
RUNNING'S SUPPLY INC
Materials
401-874-
04
7.10
10/05/2022
GEN
77568*
SARA YOUNG
DEP REFUND/APPLIED
235-000-
00
154.00
10/05/2022
GEN
77569*
SHANNON KLING
DEP REFUND/APPLIED
235-000-
00
21.00
10/05/2022
GEN
77571*
SHRED RIGHT
OFFICE SUPPLIES -SHREDDING SERVICES
401-921-
08
4.58
10/05/2022
GEN
77572*
SKYLAR BENSON
DEP REFUND/APPLIED
235-000-
00
84.00
10/05/2022
GEN
77574*
STEVEN UNLIMITED
DEP REFUND/APPLIED
235-000-
00
192.50
10/05/2022
GEN
77575*
SUSAN STUPCA
DEP REFUND/APPLIED
235-000-
00
21.00
10/05/2022
GEN
77576*
TOTAL COMPLIANCE SOLUTIONS INC
DRUG/HEARING TESTING SERVICES
401-923-
08
1,875.00
10/05/2022
GEN
77577*
UIS/SOURCECORP
COLLECTION - MATERIALS
401-903-
06
1,583.36
10/05/2022
GEN
77578*
UNDREENIKIA CAPPELEN
DEP REFUND/APPLIED
235-000-
00
42.00
10/05/2022
GEN
77579*
UNITED PARCEL SERVICE
MAIL SERVICES - UPS, FEDEX
401-921-
08
20.77
10/05/2022
GEN
77580*
VIDEOTRONIX INC
Grounds - Outside Services
401-935-
08
277.87
10/05/2022
GEN
77583*
WILLIAM OR KATHRYN WATTS
DEP REFUND/APPLIED
235-000-
00
147.00
10/05/2022
GEN
77584*
YRC FREIGHT
MAIL SERVICES - UPS, FEDEX
401-921-
08
54.87
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 22/26
Amount
Fund: 2 GAS
10/06/2022
GEN
1217(E)*
INVOICE CLOUD
collection - Materials
401-903-
06
1,473.75
10/19/2022
GEN
77585*
A & K REPAIR, INC
Grounds - Materials
401-935-
08
147.83
10/19/2022
GEN
77586*4
ACE HARDWARE
Services
107-380-
00
25.98
Services
107-380-
00
26.43
Materials
401-874-
04
19.99
Materials
401-874-
04
34.19
Materials
401-874-
04
38.46
Materials
402-892-
04
9.58
HECK GEN 77586 TOTAL FOR FUND 2:
154.63
10/19/2022
GEN
77589
BOND TRUST SERVICES CORPORATION
BOND SERVICE FEES
427-000-
08
475.00
10/19/2022
GEN
77590*4
BORDER STATES ELECTRIC SUPPLY
PLUG, SQ HEAD, MALE THRD, 1", FORGED
154-000-
00
4.52
NIPPLE, 1/4" X 4", BM, STD, SMLS, TEE
154-000-
00
13.23
NIPPLE, 3/4" X 2", BM, STD, SMLS, TEE
154-000-
00
17.80
UNION, BM, CLASS 150, 1", FEMALE THRD
154-000-
00
27.22
SALES TAX
401-874-
04
1.22
SALES TAX
401-874-
04
1.22
Materials
401-874-
04
1.87
CHECK GEN 77590 TOTAL FOR FUND 2:
67.08
10/19/2022
GEN
77591
BROWN COUNTY RURAL ELECTRIC
Utilities (Electric, Satellite
401-856-
05
198.99
10/19/2022
GEN
77592
CARTER, RONALD
Cip - Residential
401-916-
07
350.00
10/19/2022
GEN
77594
CENTURYLINK
Utilities (Electric, Satellite
401-856-
05
64.28
10/19/2022
GEN
77596*4
CINTAS CORPORATION 4470
UNIFORMS & LAUNDRY
401-880-
04
147.72
UNIFORMS & LAUNDRY
401-880-
04
147.72
UNIFORMS & LAUNDRY
401-880-
04
147.72
HECK GEN 77596 TOTAL FOR FUND 2:
443.16
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 23/26
Amount
Fund: 2 GAS
10/19/2022
GEN
7759714
CITY OF HUTCHINSON
Accounts Payable To City Of Hu
234-000-
00
143,412.25
VEHICLE/EQUIPMENT FUEL -GAS
401-880-
04
974.80
IT ADMIN AND SUPPORT 75/25
401-921-
08
6,589.82
IT ADMIN AND SUPPORT 75/25
401-921-
08
5, 186.
62
LEGAL SERVICES 75/25
401-923-
08
2,625.00
HUMAN RESOURCES SERVICES 75/25
401-923-
08
2,067.19
Utility Expenses - Water/Waste
401-930-
08
12.02
Utility Expenses - Water/Waste
401-930-
08
399.21
VEHICLES/EQUIPMENT FUEL-ADMIN 55/45
401-935-
08
32.35
HECK GEN 77597 TOTAL FOR FUND 2:
161,299.26
10/19/2022
GEN
77600*
DEMING, CORY
Cip - Residential
401-916-
07
25.00
10/19/2022
GEN
77601*
DRAGT, JENNIFER
Cip - Residential
401-916-
07
350.00
10/19/2022
GEN
77604*4
GOPHER STATE ONE -CALL INC
Materials
401-874-
04
185.
62
Line - Outside Services
401-856-
05
41.85
HECK GEN 77604 TOTAL FOR FUND 2:
227.47
10/19/2022
GEN
77606*4
HILLYARD/HUTCHINSON
Mains
107-367-
00
812.25
Mains
107-367-
00
81.21
HECK GEN 77606 TOTAL FOR FUND 2:
893.46
10/19/2022
GEN
77607*
HUTCHFIELD SERVICES INC
Grounds - Outside Services
401-935-
08
894.44
10/19/2022
GEN
77608*4
HUTCHINSON CO-OP
Vehicle/Equipment Fuel
401-880-
04
987.27
10/19/2022
GEN
77609*4
HUTCHINSON LEADER
Public Awareness - Material
401-874-
04
98.17
Public Awareness - Material
401-856-
05
98.17
Cip - Marketing
401-916-
07
80.75
HECK GEN 77609 TOTAL FOR FUND 2:
277.09
10/19/2022
GEN
77610*4
HUTCHINSON WHOLESALE SUPPLY CO
Vehicles - Material
402-895-
04
20.30
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
Fund: 2 GAS
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
10/19/2022 GEN 77612* INNOVATIVE OFFICE SOLUTIONS
10/19/2022 GEN 77613* JLR GARAGE DOOR SERVICE INC
10/19/2022 GEN 776144 KOONS GAS MEASUREMENT
10/19/2022 GEN 77620 MCKEEVER, LAUREL
10/19/2022 GEN 776214 MCLEOD COOPERATVIE POWER ASSN
Account Dept
Power Equipment - Materials
402-895-
04
Grounds - Materials
401-935-
08
HECK GEN 77610 TOTAL FOR FUND 2:
Office Supplies
401-921-
08
Office Supplies
401-921-
08
Office Supplies
401-921-
08
HECK GEN 77612 TOTAL FOR FUND 2:
Grounds - Materials
401-935-
08
Grounds - Materials
401-935-
08
HECK GEN 77613 TOTAL FOR FUND 2:
KGM0051 American Regulator, 1804PFM,
107-385-
00
SKU: 72983P10, 1/4" Orifice for 1804PFM
107-385-
00
SKU: 72983P018, 3/8" Orifice for
107-385-
00
SKU:72983P012, 1/2" Orifice for 1804PFM
107-385-
00
FREIGHT & TAX
401-874-
04
HECK GEN 77614 TOTAL FOR FUND 2:
Cip - Residential
401-916-
07
MISC EXPENSE -GAS LINE PUMP
401-880-
04
UTILITIES (ELECTRIC, SATELLITE-MCLEOD
401-856-
05
UTILITIES (ELECTRIC, SATELLITE -PIPELINE
401-856-
05
HECK GEN 77621 TOTAL FOR FUND 2:
10/19/2022 GEN 77623*
MEDICA HEALTH INSURANCE 15% GAS
242-000-
00
10/19/2022 GEN 77624*
MN MUNICIPAL UTILITIES ASSOCIATION MISC SERVICES-QTR
SAFETY/MGMT 250
401-923-
08
10/19/2022 GEN 77625
NELSON TECHNOLOGIES INC P/N# D3-0301
- Pneumatic Relay Repair
402-892-
04
P/N# A4-0010
- N300 Solenoid Valve
402-892-
04
Page 24/26
Amount
24.31
48.60
93.21
65.94
6.41
5.62
77. 97
67.50
110.78
178.28
7,701.60
302.40
302.40
302.40
905.10
9,513.90
100.00
57.73
38.66
39.56
135.95
9,025.39
1,626.19
462.00
586.00
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check #
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Payee Description
Account
Dept
Page 25/26
Amount
Fund: 2 GAS
P/N# D3-0300 - Overflo Protection
402-892-
04
326.00
P/N# D3-0131 - 7000F Pump Seal
402-892-
04
1,406.00
P/N# D3-0126 - Verometer Seal/Filter
402-892-
04
406.00
P/N# D3-0103 - Bulk Odorant Filter Kit
402-892-
04
406.00
P/N# A4-0003 - N200 Solenoid Valve
402-892-
04
562.00
P/N# C4-0104 - Odorant Filter Support
402-892-
04
158.00
P/N# BO-0087 - Actuation Piston
402-892-
04
208.00
SALES TAX
402-892-
04
324.07
HECK GEN 77625 TOTAL FOR FUND 2:
4,844.07
10/19/2022
GEN
77626
NORTHERN BORDER PIPELINE CO
LINE - OUTSIDE SERVICES -INTERCONNECT
401-856-
05
2,000.00
10/19/2022
GEN
77627*
NUVERA
TELEPHONE
401-921-
08
655.98
10/19/2022
GEN
77628*4
OXYGEN SERVICE COMPANY INC
Materials
401-874-
04
87.27
Materials
401-874-
04
72.79
HECK GEN 77628 TOTAL FOR FUND 2:
160.06
10/19/2022
GEN
77631*
PREMIUM WATERS INC
OFFICE SUPPLIES -BOTTLED WATER
401-921-
08
6.62
10/19/2022
GEN
77632*4
QUADE ELECTRIC
Materials
402-892-
04
8.41
10/19/2022
GEN
77633*
QUADIENT-LEASE
LEASE/SERVICE AGREEMENTS
401-921-
08
118.60
LEASE/SERVICE AGREEMENTS
401-921-
08
218.10
HECK GEN 77633 TOTAL FOR FUND 2:
336.70
10/19/2022
GEN
77635
REPNET, INC
Materials
401-874-
04
185.65
10/19/2022
GEN
77636
SOUTH CENTRAL ELECTRIC ASS'N
UTILITIES (ELECTRIC, SATELLITE
401-856-
05
33.00
10/19/2022
GEN
77640*4
VERIZON WIRELESS
UTILITIES (ELECTRIC, SATELLITE-SCADA
401-856-
05
156.21
TELEPHONE
401-921-
08
343.46
HECK GEN 77640 TOTAL FOR FUND 2:
499.67
10/20/2022 07:28 AM
User: JMartig
DE: Hutchinson Utili
Check Date Bank Check # Payee
CHECK DISBURSEMENT REPORT FOR HUTCHINSON UTILITIES
CHECK DATE FROM 09/23/2022 - 10/21/2022
Description
Fund: 2 GAS
10/19/2022 GEN 77642*4 WEST CENTRAL SANITATION INC
10/20/2022 GEN 1211(E)*4 BP CANANDA ENERGY SOLUTIONS
10/20/2022 GEN 1212(E) PUBLIC ENERGY AUTHORITY OF
UTILITY ESP - WATER/WASTE 45/55-
GAS FOR RETAIL
GAS FOR RETAIL
3M
HTI
UNG
BROWNTON
Utility Expenses - Water/Waste
HECK GEN 1211(E) TOTAL FOR FUND 2:
Gas For Retail
HTI
HECK GEN 1212(E) TOTAL FOR FUND 2
Total for fund 2 GAS
TOTAL - ALL FUNDS
'*'-INDICATES CHECK DISTRIBUTED TO MORE THAN ONE FUND
'#'-INDICATES CHECK DISTRIBUTED TO MORE THAN ONE DEPARTMENT
Account Dept
401-930- 08
401-807- 04
401-807- 04
401-807- 04
401-807- 04
401-807- 04
401-807- 04
401-930- 08
401-807- 04
401-807- 04
Page 26/26
Amount
228.67
;66,221.18)
730.30
208,627.73
20,205.12
870.63
1,131.29
1,264.93
166,608.82
213,235.05
60.00
213,295.05
608,044.64
2,750,253.54
HUTCHINSON UTILITIES COMMISSION
COMBINED DIVISIONS
FINANCIAL REPORT FOR SEPTEMBER, 2022
2022
2021
2
%Chnq
2022
2021
2
%Chnq
FuIIYrBud
%of Bud
Combined Division
Customer Revenue
$
2,644,126
$ 2,717,904
$ (73,778)
(2.7%)
$ 28,786,587
$ 29,290,326
$ (503,739)
(1.7%)
$ 37,355,080
77.1%
Sales for Resale
$
608,517
$ 290,214
$ 318,303
109.7%
$ 4,013,261
$ 3,143,981
$ 869,280
27.6%
$ 3,692,000
108.7%
NU Transportation
$
101,171
$ 98,016
$ 3,155
3.2%
$ 810,783
$ 782,160
$ 28,622
3.7%
$ 1,010,124
80.3%
Electric Division Transfer
$
59,724
$ 56,879
$ 2,844
5.0%
$ 537,512
$ 511,912
$ 25,600
5.0%
$ 716,383
75.0%
Other Revenues
$
54,317
$ 50,660
$ 3,657
7.2%
$ 504,635
$ 326,712
$ 177,923
54.5%
$ 479,700
105.2%
Interest Income
$
50,088
$ 42,604
$ 7,484
17.6%
$ 366,530
$ 326,956
$ 39,575
12.1%
$ 383,456
95.6%
TOTAL REVENUES
$
3,517,943
$ 3,256,277
$ 261,666
8.0%
$ 35,019,307
$ 34,382,047
$ 637,260
1.9%
$ 43,636,743
80.3%
Salaries & Benefits
$
530,090
$ 473,974
$ 56,116
11.84%
$ 5,120,467
$ 4,887,729
$ 232,738
4.8%
$ 7,270,807
70.4%
Purchased Commodities
$
1,292,887
$ 1,302,615
$ (9,729)
(0.7%)
$ 16,284,791
$ 17,984,134
$ (1,699,344)
(9.4%)
$ 19,927,587
81.7%
Transmission
$
267,625
$ 252,665
$ 14,960
5.9%
$ 2,255,789
$ 2,268,338
$ (12,549)
(0.6%)
$ 3,325,000
67.8%
Generator Fuel/Chem.
$
399,031
$ 125,602
$ 273,429
217.7%
$ 2,357,464
$ 1,308,869
$ 1,048,595
80.1%
$ 1,219,698
193.3%
Depreciation
$
375,802
$ 367,860
$ 7,942
2.2%
$ 3,399,663
$ 3,311,294
$ 88,369
2.7%
$ 4,400,000
77.3%
Transfers (Elect./City)
$
215,323
$ 212,479
$ 2,844
1.3%
$ 1,937,906
$ 1,912,306
$ 25,600
1.3%
$ 2,583,875
75.0%
Operating Expense
$
272,119
$ 237,658
$ 34,461
14.5%
$ 2,341,593
$ 1,784,675
$ 556,919
31.2%
$ 3,367,066
69.5%
Debt Interest
$
75,076
$ 83,542
$ (8,467)
(10.1%)
$ 675,680
$ 751,879
$ (76,200)
10.1%
$ 900,907
75.0%
TOTAL EXPENSES
$
3,427,953
$ 3,056,395
$ 371,558
12.2%
$ 34,373,354
$ 34,209,226
$ 164,128
0.5%
$ 42,994,940
79.9%
NET PROFIT/(LOSS)
$
89,990
$ 199,882
$ (109,892)
(55.0%)l
645,953
$ 172,822
$ 473,132
273.8%
$ 641,803
100.6%
September
September
YTD
YTD
2022 HUC
2022
2021
Change
2022
2021
Change
Budget Target
Gross Margin %:
31.1%
37.4%
-6.4%
29.0%
27.2%
1.8%
32.6%
Operating Income Per Revenue $ (%):
2.2%
6.7%
-4.4%
1.7%
0.9%
0.8%
2.2% N
Net Income Per Revenue $ (%):
2.6%
6.1%
-3.6%
1.8%
0.5%
1.3%
1.5% N
Notes/Graphs:
HUTCHINSON UTILITIES COMMISSION
ELECTRIC DIVISION
FINANCIAL REPORT FOR SEPTEMBER, 2022�y�
QQQyyg�
J
ry QQQ
2022
2021 2 %Chna 2022 2021
2
%Chna
Full YrBud
%ofBud
Electric Division
Customer Revenue
$
2,080,942
$ 2,201,899 $ (120,957) (5.5%) $ 19,162,976 $ 19,327,588
$ (164,612)
(0.9%)
$ 25,325,244
75.7%
Sales for Resale
$
608,517
$ 290,214 $ 318,303 109.7% $ 4,013,261 $ 3,143,981
$ 869,280
27.6%
$ 3,692,000
108.7%
Other Revenues
$
23,266
$ 17,081 $ 6,185 36.2% $ 235,571 $ 114,832
$ 120,739
105.1%
$ 188,599
124.9%
Interest Income
$
26,438
$ 22,703 $ 3,735 16.5% $ 195,847 $ 175,972
$ 19,874
11.3%
$ 208,456
94.0%
TOTAL REVENUES
$
2,739,163
$ 2,531,896 $ 207,267 8.2% $ 23,607,655 $ 22,762,374
$ 845,281
3.7%
$ 29,414,299
80.3%
Salaries & Benefits
$
408,290
$ 343,741
$ 64,550
18.8%
$ 3,892,855
$ 3,624,281
$ 268,574
7.4%
$
5,319,511
73.2%
Purchased Power
$
932,750
$ 1,049,143
$ (116,393)
(11.1%)
$ 9,896,110
$ 10,291,614
$ (395,504)
(3.8%)
$ 12,297,526
80.5%
Transmission
$
267,625
$ 252,665
$ 14,960
5.9%
$ 2,255,789
$ 2,268,338
$ (12,549)
(0.6%)
$
3,325,000
67.8%
Generator Fuel/Chem.
$
399,031
$ 125,602
$ 273,429
217.7%
$ 2,357,464
$ 1,308,869
$ 1,048,595
80.1%
$
1,219,698
193.3%
Depreciation
$
285,780
$ 276,321
$ 9,459
3.4%
$ 2,579,192
$ 2,487,885
$ 91,307
3.7%
$
3,300,000
78.2%
Transfers (Elect./City)
$
167,519
$ 164,674
$ 2,844
1.7%
$ 1,507,669
$ 1,482,070
$ 25,600
1.7%
$
2,010,226
75.0%
Operating Expense
$
207,195
$ 173,126
$ 34,069
19.7%
$ 1,661,443
$ 1,213,903
$ 447,540
36.9%
$
1,928,042
86.2%
Debt Interest
$
40,071
$ 43,321
$ (3,250)
(7.5%)
$ 360,642
$ 389,892
$ (29,250)
JL
$
480,857
75.0%
TOTAL EXPENSES
$
2,708,262
$ 2,428,594
$ 279,668
11.5%
$ 24,511,164
$ 23,066,852
$ 1,444,312
6.3%
$
29,880,860
82.0%
NET PROFIT/(LOSS)
$
30,901
$ 103,302
$ (72,401)
(70.1%)
$ (903,510)
$ (304,478)
$ (599,032)
196.7%
$
(466,561)
193.7%
2022
2021
2
%Chna
2022
2021
2
%Chna
Full YrBud
%ofBud
Electric Division
Residential
4,247,602
4,060,878
186,724
4.60%
41,459,679
41,665,983
(206,304)
(0.50%)
54,152,764
76.6%
All Electric
128,710
121,278
7,432
6.13%
2,026,206
1,878,401
147,805
7.87%
2,641,117
76.7%
Small General
1,441,078
1,376,378
64,700
4.70%
13,878,954
13,801,448
77,506
0.56%
18,688,349
74.3%
Large General
7,150,180
7,375,870
(225,690)
(3.06%)
64,507,970
65,019,130
(511,160)
(0.79%)
83,253,310
77.5%
Industrial
9,099,000
10,275,000
(1,176,000)
(11.45%)
88,928,000
92,405,000
(3,477,000)
(3.76%)
122,088,679
72.8%
Total KWH Sold
22,066,570
23,209,404
(1,142,834)
(4.92%)
210,800,809
214,769,962
(3,969,153)
(1.85%)
280,824,218
75.1%
September
September
YTD
YTD
2022
HUC
2022
2021
Change
2022
2021
Change
Budget
Target
Gross Margin %: 26.8% 31.3% -4.5% 23.7% 25.7% -2.0% 29.2% 24%-28%
Operating Income Per Revenue $ (%):
1.2%
4.9%
-3.7%
-3.7%
-0.8%
-2.9%
-0.7%
Net Income Per Revenue $ (%):
1.1%
4.1%
-3.0%
-3.8%
-1.3%
-2.5%
-1.6%
Customer Revenue per KWH:
$0.0943
$0.0949
-$0.0006
$0.0909
$0.0900
$0.0009
$0.0902
Total Power Supply Exp. per KWH: $0.0896 $0.0742 $0.0154 $0.0843 $0.0778 $0.0065 $0.0736 $0.0736
Net Income decreased by $72,401 over September 2021. The primary reason for this decrease was the increased cost of generator fuels due to increased
generation that were offset by higher sales for resale. All other expenses were up as well except purchased power due to less power purchased even though
the cost per mwh was higher.
Sales for Resale of $608,517 consisted of $154,455 in market sales, $98,000 in capacity sales to Rice Lake, $146,250 in capacity sales to AEP, and $209,812
in Tolling agreement sales to Dynasty Power. September 2021 Sales for Resale of $290,214 included $45,964 in market sales, $146,250 in capacity sales to AEP, and
$98,000 in capacity sales to Rice Lake. September 2020 Sales for Resale of $249,342 consisted of $5,092 in market sales, $146,250 in capacity sales to AEP, and
$98,000 in capacity sales to Rice Lake.
Overall Purchased Power decreased by $116,393. MRES purchases decreased by $34,392 and market purchases/MISO costs decreased by $82,001.
The average cost of MISO power was $46.55/mwh (3,048 mwh's purchased), compared to $37.79/mwh (4,251 mwh's purchased) in September 2021.
Power Cost Adjustment for September 2022 was $.00455 bringing in an additional $100,794 for the month and $1,143,575 YTD.
Power Cost Adjustment for September 2021 was $.00762 bringing in an additional $177,056 for the month and $1,183,022 YTD.
HUTCHINSON UTILITIES COMMISSION
GAS DIVISION
FINANCIAL REPORT FOR SEPTEMBER, 2022
2022
2021
Di .
%Chna
2022
2021
Di .
%Chna
Full YrBud
%of Bud
Gas Division
Customer Revenue
$
563,184
$ 516,005
$ 47,179
9.1%
$ 9,623,611
$
9,962,738
$
(339,127)
(3.4%)
$
12,029,836
80.0%
Transportation
$
101,171
$ 98,016
$ 3,155
3.2%
$ 810,783
$
782,160
$
28,622
3.7%
$
1,010,124
80.3%
Electric Div. Transfer
$
59,724
$ 56,879
$ 2,844
5.0%
$ 537,512
$
511,912
$
25,600
5.0%
$
716,383
75.0%
Other Revenues
$
31,051
$ 33,579
$ (2,528)
(7.5%)
$ 269,064
$
211,880
$
57,184
27.0%
$
291,101
92.4%
Interest Income
$
23,650
$ 19,902
$ 3,749
18.8%
$ 170,683
$
150,983
$
19,700
13.0%
$
175,000
97.5%
TOTAL REVENUES
$
778,779
$ 724,381
$ 54,398
7.5%
$ 11,411,653
$
11,619,673
$
(208,021)
(1.8%)
$
14,222,444
80.2%
Salaries & Benefits
$
121,800
$ 130,234
$ (8,434)
(6.5%)
$ 1,227,613
$
1,263,448
$
(35,835)
(2.8%)
$
1,951,296
62.9%
Purchased Gas
$
360,137
$ 253,472
$ 106,665
42.1%
$ 6,388,681
$
7,692,521
$
(1,303,840)
(16.9%)
$
7,630,061
83.7%
Operating Expense
$
64,924
$ 64,532
$ 392
0.6%
$ 680,150
$
570,772
$
109,378
19.2%
$
1,439,024
47.3%
Depreciation
$
90,022
$ 91,539
$ (1,517)
(1.7%)
$ 820,471
$
823,409
$
(2,937)
(0.4%)
$
1,100,000
74.6%
Transfers (City)
$
47,804
$ 47,804
$
0.0%
$ 430,237
$
430,237
$
0
0.0%
$
573,649
75.0%
Debt Interest
$
35,004
$ 40,221
$ (5,217)
0.0%
$ 315,038
$
361,987
$
(46,950)
13.0%
$
420,050
75.0%
TOTAL EXPENSES
$
719,691
$ 627,801
$ 91,890
14.6%
$ 9,862,190
$
11,142,374
$
(1,280,184)
(11.5%)
$
13,114,080
75.2%
NET PROFIT/(LOSS)
$
59,088
$ 96,580
$ (37,492)
(38.8%)l
$ 1,549,463
$
477,300
$
1,072,163
224.6%
$
1,108,364
139.8%
2022
2021
Di
%Chnq
2022
2021
Di
%Chnq
Full YrBud
%of Bud
Gas Division
Residential
7,743,247
6,657,691
1,085,556
16.31%
317,051,645
259,911,925
57,139,720
21.98%
439,919,000
72.1%
Commercial
8,949,524
8,035,975
913,549
11.37%
247,596,671
205,569,934
42,026,737
20.44%
347,946,000
71.2%
Industrial
47,985,276
51,142,736
(3,157,460)
(6.17%)
658,039,506
618,262,674
39,776,832
6.43%
873,587,000
75.3%
Total CF Sold
64,678,047
65,836,402
(1,158,355)
(1.76%)
1,222,687,822
1,083,744,533
138,943,289
12.82%
1,661,452,000
73.6%
September
September
YTD
YTD
2022 HUC
2022
2021
Change
2022
2021
Change
Budget Target
Gross Margin %:
46.9%
60.1%
-13.2%
40.3%
30.3%
10.1%
39.9%
Operating Income Per Revenue $ (%):
5.9%
13.2%
-7.2%
13.3%
4.3%
9.0%
8.2%
Net Income Per Revenue $ (%):
7.6%
13.3%
-5.7%
13.6%
4.1%
9.5%
7.8%
Contracted Customer Rev. per CF:
$0.0063
$0.0047
$0.0016
$0.0063
$0.0066
-$0.0003
$0.0056
Customer Revenue per CF:
$0.0138
$0.0160
-$0.0021
$0.0095
$0.0123
-$0.0028
$0.0088
Total Power Supply Exp. per CF:
$0.0060
$0.0041
$0.0019
$0.0054
$0.0072
($0.0019)
$0.0050 $0.0050
September 2022 net income decreased by $37,492 mainly due to the increased purchased gas costs.
September 2022 fuel cost credit adjustment was zero for the month and $20,473 YTD.
September 2021 fuel cost adjustment was $1.42 per MCF which brought in $25,954 for the month with a total of $1,140,042 YTD.
Current Assets
UnrestrictedlUndesignated Cash
Cash
Petty Cash
Designated Cash
Capital Expenditures - Five Yr. CIP
Payment in Lieu of Taxes
Rate Stabilization - Electric
Rate Stabilization - Gas
Catastrophic Funds
Restricted Cash
Bond Interest Payment 2017
Bond Interest Payment 2012
Debt Service Reserve Funds
Total Current Assets
Receivables
Accounts (net of uncollectible allowances)
Interest
Total Receivables
Other Assets
Inventory
Prepaid Expenses
Sales Tax Receivable
Deferred Outflows - Electric
Deferred Outflows - Gas
Total Other Assets
Total Current Assets
Capital Assets
Land & Land Rights
Depreciable Capital Assets
Accumulated Depreciation
Construction - Work in Progress
Total Net Capital Assets
Total Assets
HUTCHINSON UTILITIES COMMISSION
BALANCE SHEET - CONSOLIDATED
SEPTEMBER 30, 2022
Electric Gas Total
Division Division 2022
Total Net Change
2021 Total (YTD)
6,206,154.74
11,532,890.42
17,739,045.16
16,779,723.97
959,321.19
680.00
170.00
850.00
850.00
-
2,750,000.00
700,000.00
3,450,000.00
3,450,000.00
-
1,293,543.00
573,649.00
1,867,192.00
1,867,192.00
-
395,204.99
-
395,204.99
364,336.05
30,868.94
-
607,452.34
607,452.34
448,570.40
158,881.94
800,000.00
200,000.00
1,000,000.00
1,000,000.00
-
1,443,618.67
-
1,443,618.67
1,685,713.60
(242,094.93)
-
1,581,683.34
1,581,683.34
1,706,375.00
(124,691.66)
522,335.64
2,188,694.02
2,711,029.66
2,711,029.66
-
13,411,537.04
17,384,539.12
30,796,076.16
30,013,790.68
782,285.48
2,446,079.01
715,114.35
3,161,193.36
3,015,894.89
145,298.47
47,207.51
47,207.50
94,415.01
97,985.30
(3,570.29)
2,493,286.52
762,321.85
3,255,608.37
3,113,880.19
141,728.18
1,629,414.41
518,865.05
2,148,279.46
2,171,519.92
(23,240.46)
(65,022.96)
26,932.43
(38,090.53)
160,599.21
(198,689.74)
193,607.95
-
193,607.95
134,181.45
59,426.50
1,630,746.00
-
1,630,746.00
313,166.00
1,317,580.00
-
543,582.00
543,582.00
104,390.00
439,192.00
3,388,745.40
1,089,379.48
4,478,124.88
2,883,856.58
1,594,268.30
19,293,568.96
19,236,240.45
38,529,809.41
36,011,527.45
2,518,281.96
690,368.40
3,899,918.60
4,590,287.00
4,590,287.00
-
111,117,442.08
42,656,015.41
153,773,457.49
150,779,681.28
2,993,776.21
(66,266,045.29)
(19,992,598.78)
(86,258,644.07)
(82,074,790.90)
(4,183,853.17)
1,132,856.53
392,464.57
1,525,321.10
3,018,128.42
(1,492,807.32)
46,674,621.72
26,955,799.80
73,630,421.52
76,313,305.80
(2,682,884.28)
65,968,190.68
46,192,040.25
112,160,230.93
112,324,833.25
(164,602.32)
Current Liabilities
Current Portion of Long-term Debt
Bonds Payable
Bond Premium
Accounts Payable
Accrued Expenses
Accrued Interest
Accrued Payroll
Total Current Liabilities
Long -Term Liabilities
Noncurrent Portion of Long-term Debt
2017 Bonds
2012 Bonds
Bond Premium 2012
Pension Liability- Electric
Pension Liability - Electric OPEB
Pension Liability - Nat Gas
Pension Liability - Nat Gas OPEB
Accrued Vacation Payable
Accrued Severance
Deferred Outflows - Electric
Deferred Outflows - Nat Gas
Total Long -Term Liabilities
Net Position
Retained Earnings
Total Net Position
HUTCHINSON UTILITIES COMMISSION
BALANCE SHEET - CONSOLIDATED
SEPTEMBER 30, 2022
Electric Gas Total
Division Division 2022
700,000.00
2,012,050.99
160,285.44
53,967.30
2,926,303.73
14,030,000.00
507,430.56
2,219,565.00
94,162.00
431,660.51
91,639.00
2,041,393.00
19,415,850.07
1,730,000.00
185,608.32
600,714.78
140,016.68
17, 000.18
2,673,339.96
7,780,000.00
587,759.31
739,855.00
31,387.00
163,481.47
31,615.85
680,464.00
10,014,562.63
2,430,000.00
185,608.32
2,612,765.77
300,302.12
70,967.48
5,599,643.69
14,030,000.00
7,780,000.00
1,095,189.87
2,219,565.00
94,162.00
739,855.00
31,387.00
595,141.98
123,254.85
2,041,393.00
680,464.00
29,430,412.70
Total
2021
2,240,000.00
185,608.32
2,917,912.81
339,168.49
63,175.37
5,745,864.99
14,730,000.00
9,510,000.00
1,314,255.15
3,026,207.00
84,054.00
1,008,736.00
28,018.00
584,864.37
124,387.07
123,417.00
41,139.00
30,575,077.59
Net Change
Total (YTD)
190,000.00
(305,147.04)
(38,866.37)
7,792.11
(146,221.30)
(700,000.00)
(1,730,000.00)
(219,065.28)
(806,642.00)
10,108.00
(268,881.00)
3,369.00
10,277.61
(1,132.22)
1,917,976.00
639,325.00
(1,144,664.89)
43,626,036.88 33,504,137.66 77,130,174.54 76,003,890.67 1,126,283.87
43,626,036.88 33,504,137.66 77,130,174.54 76,003,890.67 1,126,283.87
Total Liabilities and Net Position 65,968,190.68 46,192,040.25 112,160,230.93 112,324,833.25 (164,602.32)
Hutchinson Utilities Commission
Cash -Designations Report, Combined
September 30, 2022
Change in
Financial
Annual
Balance,
Balance,
Cash/Reserve
Institution
Current Interest Rate
Interest
September 2022
August 2022
Position
Savings, Checking, Investments varies
Total Operating Funds
varies varies 30,796,076.16 30,089,863.84 706,212.32
Debt Reserve Requirements Bond Covenants - sinking fund
Debt Reserve Requirements Bond Covenants -1 year Max. P & I
Total Restricted Funds
30,796,076.16 30,089,863.84 706,212.32
3,025,302.01 2,747,726.48 277,575.53
2,711,029.66 2,711,029.66 -
5,736,331.67 5,458,756.14 277,575.53
Operating Reserve
Min 60 days of 2022 Operating Bud.
6,432,490.00
6,432,490.00
Rate Stabalization Funds
1,002,657.33
1,023,879.38 (21,222.05)
PILOT Funds
Charter (Formula Only)
1,867,192.00
1,867,192.00
Catastrophic Funds
Risk Mitigation Amount
1,000,000.00
1,000,000.00
Capital Reserves
5 Year CIP (2022-2026 Fleet & Infrastructure Maintenance)
3,450,000.00
3,450,000.00
Total Designated Funds
13,752,339.33
13,773,561.38 (21,222.05)
YE
YE
YE
YE
YTD
HUC
2018
2019
2020
2021
2022
Target
Debt to Asset 37.7%
34.9%
32.3%
30.8%
31.2%
Current Ratio 3.93
5.11
5.67
5.22
5.47
RONA 3.16%
2.25%
3.62%
0.41%
0.65%
Change in
Cash Balance (From 12131114 to
913012022)
Month End
Electric
Elec. Change
Natural Gas
Gas Change
Total
Total Change
9/30/202 2
13,411,537
17, 384, 539
30, 796, 076
12/31/2021
12,870,253
541,284
15,086,000
2,298,539
27,956,253
2,839,823
12/31/2020
14,239,233
(1,368,981)
15,019,173
66,827
29,258,406
(1,302,153)
12/31/2019
12,124,142
2,115,092
13,837,040
1,182,133
25,961,181
3,297,225
12/31/2018
15,559,867
(3,435,725)
12,335,998
1,501,042
27,895,864
(1,934,683)
12/31/2017
23,213,245
(7,653,378)
10,702,689
1,633,309
33,915,934
(6,020,070)
12/31/2016
8,612,801
14,600,444
9,500,074
1,202,615
18,112,875
15,803,059
12/31/2015
6,170,790
2,442,011
9,037,373
462,701
15,208,163
2,904,712
12/31/2014
3,598,821
2,571,969
6,765,165
2,272,208
10,363,986
4,844,177
* 2017's Significant increase in cash balance is due to issuing bonds for the generator project.
Hutchinson Utilities Commission
Cash -Designations Report, Electric
September 30, 2022
Change in
Financial
Annual
Balance,
Balance,
Cash/Reserve
Institution
Current Interest Rate
Interest
September 2022
August 2022
Position
Savings, Checking, Investments varies varies varies 30,796,076.16 30,089,863.84 706,212.32
Total HUC Operating Funds 30,796,076.16 30,089,863.84 706,212.32
Debt Restricted Requirements
Debt Restricted Requirements
Total Restricted Funds
Bond Covenants - sinking fund
Bond Covenants -1 year Max. P & 1
1,443,618.67
522,335.64
1,965,954.31
1,345,213.98
522,335.64
1,867,549.62
98,404.69
-
98,404.69
Excess Reserves Less Restrictions,
Electric
11,445,582.73
11,114,093.41
331,489.32
1�1
Operating Reserve
Min 60 days of 2022 Operating Bud.
4,430,143.33
4,430,143.33
-
Rate Stabalization Funds
$400K-$1.2K
395,204.99
395,204.99
PILOT Funds
Charter (Formula Only)
1,293,543.00
1,293,543.00
Catastrophic Funds
Risk Mitigation Amount
800,000.00
800,000.00
Capital Reserves
5 Year CIP (2022-2026 Fleet & Infrastructure Maintenance)
2,750,000.00
2,750,000.00
Total Designated Funds
9,668,891.32
9,668,891.32
-
Excess Reserves Less Restrictions
& Designations, Electric
1,776,691.41
1,445,202.09
331,489.32
YE YE YE YE
YTD
APPA Ratio
HUC
2018 2019 2020 2021
2022
5K-10K Cust.
Target
Debt to Asset Ratio (* w/Gen.)
35.7% 34.1% 32.6% 32.2%
33.9%
39.8%
ONE
Current Ratio
3.63 5.26 6.18 5.70
5.36
3.75
RONA
-0.3% -0.4% 2.5% -1.2%
-1.5%
NA
>0%
Hutchinson Utilities Commission
Cash -Designations Report, Gas
September 30, 2022
Change in
Financial
Annual
Balance,
Balance,
Cash/Reserve
Institution
Current Interest Rate
Interest
September 2022
August 2022
Position
Savings, Checking, Investments varies varies
Total HUC Operating Funds
Debt Restricted Requirements Bond Covenants - sinking fund
Debt Restricted Requirements Bond Covenants -1 year Max. P & I
Total Restricted Funds
varies 30,796,076.16 30,089,863.84 706,212.32
30,796,076.16 30,089,863.84 706,212.32
1, 581, 683.34 1, 402, 512.50 179,170.84
2,188,694.02 2,188,694.02 -
3,770,377.36 3,591,206.52 179,170.84
Operating Reserve
Min 60 days of 2022 Operating Bud.
2,002,346.67
2,002,346.67
Rate Stabalization Funds
$200K-$600K
607,452.34
628,674.39 (21,222.05)
PILOT Funds
Charter (Formula Only)
573,649.00
573,649.00
Catastrophic Funds
Risk Mitigation Amount
200,000.00
200,000.00
Capital Reserves
5 Year CIP ( 2022-2026 Fleet & Infrastructure Maintenance)
700,000.00
700,000.00
Total Designated Funds
4,083,448.01
4,104,670.06 (21,222.05)
YE
YE
YE
YE
YTD
HUC
2018
2019
2020
2021
2022
AGA Ratio
Target
Debt to Asset 40.7%
36.1%
32.0%
28.8%
27.5%
35%-50%
Current Ratio 4.33
4.96
5.18
4.79
5.58
1.0-3.0
RONA 8.3%
6.4%
5.3%
2.9%
4.0%
2%-5%
HUTCHINSON UTILITIES COMMISSION
Investment Report
For the Month Ended September 30, 2022
Interest
Current
Date of
Date of
Par
Current
Purchase
Unrealized
Premium
Next
Institution
Description
Rate
YTM
Purchase
Maturity
Value
Value
Amount
Gain/(Loss)
(Discount)
Call Date
Wells Fargo
Money Market
1.950%
1.950%
NA
NA
-
20,207.86
-
-
-
N/A
Wells Fargo
US Treasury Note
1.625%
1.414%
06/07/2022
12/152022
1,000,000.00
996,990.00
1,001,090.63
(4,100.63)
1,090.63
N/A
Wells Fargo
US Treasury Note
2.375%
1.677%
06/07/2022
01/312023
1,000,000.00
995,620.00
1,004,471.88
(8,851.88)
4,471.88
N/A
Wells Fargo
US Treasury Note
2.500 %
1.942%
06/07/2022
03/312023
1,000,000.00
993,550.00
1,004,471.88
(10,921.88)
4,471.88
N/A
Wells Fargo
US Treasury Note
2.750 %
2.128%
06/07/2022
05/312023
1,000,000.00
991,280.00
1,006,000.00
(14,720.00)
6,000.00
N/A
Wells Fargo
FHLB
0.400%
0.587%
01/29/2021
01292026
295,000.00
260,266.70
295,000.00
(34,733.30)
-
01/29/2023
Wells Fargo
FHLB
0.400%
0.525%
02/09/2021
02/092026
470,000.00
413,242.80
470,000.00
(56,757.20)
-
02/09/2023
Wells Fargo
FHLB
0.750%
1.432%
04/29/2021
04292026
400,000.00
362,376.00
400,000.00
(37,624.00)
-
12/29/2022
Wells Fargo
FHLB
0.650%
1.069%
06/30/2021
06/302026
300,000.00
264,588.00
300,000.00
(35,412.00)
-
12/30/2022
Wells Fargo
FHLB
0.600 %
1.281 %
09/30/2021
09/302026
250,000.00
220,662.50
250,000.00
(29,337.50)
-
12/30/2022
Wells Fargo
CD's
2.550%
2.550%
06/17/2022
12/182023
245,000.00
240,283.75
245,000.00
(4,716.25)
-
N/A
Wells Fargo
CD's
0.300%
0.300%
01/08/2021
01/082024
245,000.00
233,208.15
245,000.00
(11,791.85)
-
N/A
Wells Fargo
CD's
0.450%
0.450%
04/14/2021
04/152024
245,000.00
231,196.70
245,000.00
(13,803.30)
-
02/14/2023
Wells Fargo
CD's
2.800%
2.800%
06/17/2022
06/172024
245,000.00
239,139.60
245,000.00
(5,860.40)
-
N/A
Wells Fargo
CD's
0.550%
0.550%
08/02/2021
08/052024
245,000.00
228,874.10
245,000.00
(16,125.90)
-
N/A
Wells Fargo
CD's
1.100%
1.100%
01/31/2022
01/312025
245,000.00
227,580.50
245,000.00
(17,419.50)
-
01/31/2023
Wells Fargo
CD's
1.600%
1.600%
02/23/2022
02242025
245,000.00
229,905.55
245,000.00
(15,094.45)
-
N/A
Wells Fargo
CD's
3.100%
3.100%
06/15/2022
06/162025
245,000.00
237,316.80
245,000.00
(7,683.20)
-
N/A
Wells Fargo
CD's
3.100%
3.100%
06/15/2022
06/162025
245,000.00
237,316.80
245,000.00
(7,683.20)
-
N/A
Wells Fargo
CD's
3.300%
3.300%
08/26/2022
08262025
245,000.00
238,051.80
245,000.00
(6,948.20)
-
N/A
Wells Fargo
CD's
1.000%
1.000%
05/19/2021
05/192026
245,000.00
217,648.20
245,000.00
(27,351.80)
-
N/A
Wells Fargo
CD's
1.000%
1.000%
07/28/2021
07282026
245,000.00
215,722.50
245,000.00
(29,277.50)
-
N/A
Wells Fargo
CD's
1.050%
1.050%
08/08/2021
08252026
238,000.00
210,027.86
238,000.00
(27,972.14)
-
N/A
Wells Fargo
CD's
1.000%
1.207%
07/31/2021
07/132028
245,000.00
205,087.05
245,000.00
(39,912.95)
12/13/2022
Broker Total
49.2%
9,138,000.00
8,710,143.22
9,154,034.39
(464,099.03)
16,034.39
Cetera Investment Services
Money Market
0.110%
0.110%
N/A
N/A
-
1,780.79
-
-
-
N/A
Cetera Investment Services
Municipal Bonds
3.650%
3.004%
12/20/2018
02/012023
250,000.00
249,575.00
256,165.00
(6,590.00)
6,165.00
N/A
Cetera Investment Services
Municipal Bonds
3.240%
3.240%
11/17/2017
02/152023
80,000.00
78,804.00
69,633.48
9,170.52
(10,366.52)
N/A
Cetera Investment Services
Municipal Bonds
3.075%
3.236%
12/20/2018
06/012023
50,000.00
49,548.00
49,746.15
(198.15)
(253.85)
N/A
Cetera Investment Services
Municipal Bonds
5.290%
2.724%
04/18/2019
06/012023
260,000.00
260,925.60
291,059.96
(30,134.36)
31,059.96
N/A
Cetera Investment Services
Municipal Bonds
2.500 %
3.181 %
12/20/2018
08/012023
35,000.00
34,375.95
34,320.05
55.90
(679.95)
N/A
Cetera Investment Services
Municipal Bonds
3.400%
3.148%
12/20/2018
11/012023
125,000.00
123,632.50
126,376.25
(2,743.75)
1,376.25
N/A
Cetera Investment Services
Municipal Bonds
3.400%
3.148%
12/20/2018
11/012023
65,000.00
64,288.90
65,715.65
(1,426.75)
715.65
N/A
Cetera Investment Services
Municipal Bonds
2.854%
3.173%
12/20/2018
02/012024
100,000.00
97,911.00
99,605.96
(1,694.96)
(394.04)
N/A
Cetera Investment Services
Municipal Bonds
2.977%
3.246%
12/20/2018
03/152024
250,000.00
244,260.00
248,743.99
(4,483.99)
(1,256.01)
N/A
Cetera Investment Services
Municipal Bonds
1.940 %
1.821 %
01/13/2020
05/012024
65,000.00
62,537.15
65,570.70
(3,033.55)
570.70
N/A
Cetera Investment Services
Municipal Bonds
5.742%
3.658%
04/11/2019
08/012024
190,000.00
193,587.20
208,924.00
(15,336.80)
18,924.00
N/A
Cetera Investment Services
Municipal Bonds
2.400%
2.908%
08/05/2022
08/152024
50,000.00
47,876.00
50,070.17
(2,194.17)
70.17
N/A
Cetera Investment Services
Municipal Bonds
2.402%
2.926%
08/05/2022
10/012024
125,000.00
120,042.50
124,674.19
(4,631.69)
(325.81)
N/A
Cetera Investment Services
Municipal Bonds
2.528%
1.918%
01/13/2020
12/012024
100,000.00
95,262.00
102,999.53
(7,737.53)
2,999.53
N/A
Cetera Investment Services
Municipal Bonds
1.319%
4.407%
09/26/2022
12/012024
50,000.00
46,525.50
47,238.35
(712.85)
(2,761.65)
N/A
Cetera Investment Services
Municipal Bonds
3.922%
3.429%
12/20/2018
12/012024
204,000.00
201,074.64
208,181.10
(7,106.46)
4,181.10
N/A
Cetera Investment Services
Municipal Bonds
4.400%
3.221 %
04/11/2019
07/012025
500,000.00
484,485.00
539,101.11
(54,616.11)
39,101.11
07/01/2023
Cetera Investment Services
Municipal Bonds
5.640%
3.007%
04/18/2019
08/152025
205,000.00
178,827.65
169,737.95
9,089.70
(35,262.05)
N/A
Cetera Investment Services
Municipal Bonds
3.743%
2.740%
04/18/2019
09/152025
215,000.00
208,446.80
228,334.53
(19,887.73)
13,334.53
N/A
Cetera Investment Services
Municipal Bonds
3.379%
1.934%
08/19/2019
10/012025
310,000.00
297,348.90
339,739.18
(42,390.28)
29,739.18
N/A
Cetera Investment Services
Municipal Bonds
2.727 %
2.271 %
03/03/2022
12/012025
335,000.00
309,998.95
342,781.72
(32,782.77)
7,781.72
N/A
Cetera Investment Services
Municipal Bonds
5.600%
1.186%
07/28/2020
12/012025
45,000.00
46,138.95
55,250.55
(9,111.60)
10,250.55
N/A
Cetera Investment Services
Municipal Bonds
4.250%
3.258%
04/11/2019
01/012026
500,000.00
493,500.00
529,769.03
(36,269.03)
29,769.03
N/A
Cetera Investment Services
Municipal Bonds
2.420%
1.175%
10/06/2020
03/012026
100,000.00
92,470.00
106,734.28
(14,264.28)
6,734.28
N/A
Cetera Investment Services
Municipal Bonds
1.609%
1.124%
09/24/2020
04/012026
285,000.00
256,719.45
292,370.10
(35,650.65)
7,370.10
N/A
Cetera Investment Services
Municipal Bonds
6.690%
3.356%
04/18/2019
04/152026
60,000.00
49,338.60
47,545.20
1,793.40
(12,454.80)
N/A
Cetera Investment Services
Municipal Bonds
5.900 %
1.451 %
07/28/2020
06/152026
75,000.00
77,968.50
93,741.75
(15,773.25)
18,741.75
N/A
Cetera Investment Services
Municipal Bonds
0.000%
1.415%
08/13/2020
07/012026
100,000.00
82,780.00
92,037.00
(9,257.00)
(7,963.00)
N/A
Cetera Investment Services
Municipal Bonds
3.250%
2.903%
04/18/2019
08/012026
500,000.00
470,920.00
514,790.69
(43,870.69)
14,790.69
N/A
Cetera Investment Services
Municipal Bonds
2.116%
3.307%
06/07/2022
08/012026
75,000.00
67,755.75
71,565.00
(3,809.25)
(3,435.00)
N/A
Cetera Investment Services
Municipal Bonds
2.150%
2.203%
07/01/2019
12/012026
40,000.00
36,470.00
40,150.64
(3,680.64)
150.64
N/A
Cetera Investment Services
Municipal Bonds
1.664%
1.150%
08/27/2020
09/012026
225,000.00
200,513.25
231,696.00
(31,182.75)
6,696.00
N/A
Cetera Investment Services
Municipal Bonds
2.375%
1.816%
09/04/2019
12/012026
90,000.00
82,405.80
93,395.70
(10,989.90)
3,395.70
N/A
Cetera Investment Services
Municipal Bonds
2.350 %
2.191 %
07/01/2019
12/012026
500,000.00
457,255.00
505,385.00
(48,130.00)
5,385.00
N/A
Cetera Investment Services
Municipal Bonds
3.000 %
1.991 %
08/19/2019
02/012027
50,000.00
46,665.00
53,551.00
(6,886.00)
3,551.00
N/A
Cetera Investment Services
Municipal Bonds
3.150%
2.034%
08/19/2019
03/152027
100,000.00
94,228.00
109,138.50
(14,910.50)
9,138.50
N/A
Cetera Investment Services
Municipal Bonds
3.332%
3.120%
04/18/2019
04/152027
500,000.00
468,420.00
507,783.94
(39,363.94)
7,783.94
N/A
Cetera Investment Services
Municipal Bonds
3.865%
2.470%
08/19/2019
05/012027
55,000.00
53,970.40
60,986.48
(7,016.08)
5,986.48
05/01/2025
Interest
Current
Date of
Date of
Par
Current
Purchase
Unrealized
Premium
Next
Institution
Description
Rate
YTM
Purchase
Maturity
Value
Value
Amount
Gain/(Loss)
(Discount)
Call Date
Cetera
Investment Services
Municipal Bonds
3.553%
2.289%
08/19/2019
05/01/2027
55,000.00
52,465.05
60,468.04
(8,002.99)
5,468.04
05/01/2026
Cetera
Investment Services
Municipal Bonds
3.230%
1.828%
08/19/2019
05/15/2027
145,000.00
135,973.75
160,827.31
(24,853.56)
15,827.31
N/A
Cetera
Investment Services
Municipal Bonds
1.925%
1.719%
11/23/2021
06/01/2027
310,000.00
271,563.10
313,447.46
(41,884.36)
3,447.46
Make -Whole Call
Cetera
Investment Services
Municipal Bonds
1.861 %
1.254%
06/07/2021
07/01/2027
410,000.00
356,741.00
412,336.71
(55,595.71)
2,336.71
N/A
Cetera
Investment Services
Municipal Bonds
3.000%
3.101%
05/18/2020
09/01/2027
65,000.00
62,692.50
69,180.58
(6,488.08)
4,180.58
09/01/2025
Cetera
Investment Services
Municipal Bonds
2.817%
2.817%
09/25/2019
10/01/2027
35,000.00
27,156.85
27,969.55
(812.70)
(7,030.45)
05/01/2025
Cetera
Investment Services
Municipal Bonds
1.415%
1.793%
11/23/2021
03/01/2028
100,000.00
84,100.00
98,088.31
(13,988.31)
(1,911.69)
N/A
Cetera
Investment Services
Municipal Bonds
3.270%
2.141 %
08/19/2019
03/15/2028
155,000.00
142,737.95
170,805.09
(28,067.14)
15,805.09
09/15/2027
Cetera
Investment Services
Municipal Bonds
2.974%
2.574%
11/07/2019
04/01/2028
75,000.00
67,705.50
77,253.00
(9,547.50)
2,253.00
N/A
Cetera
Investment Services
Municipal Bonds
2.125%
1.904%
11/23/2021
O6/01/2028
110,000.00
94,614.30
111,525.06
(16,910.76)
1,525.06
N/A
Cetera
Investment Services
Municipal Bonds
2.547%
1.240%
08/10/2021
07/01/2028
125,000.00
109,890.00
136,101.16
(26,211.16)
11,101.16
N/A
Cetera
Investment Services
Municipal Bonds
3.140%
2.004%
08/19/2019
08/01/2028
500,000.00
454,400.00
547,105.00
(92,705.00)
47,105.00
08/01/2027
Cetera
Investment Services
Municipal Bonds
3.000%
2.199%
05/19/2020
08/15/2028
90,000.00
85,591.80
95,401.80
(9,810.00)
5,401.80
08/15/2025
Cetera
Investment Services
Municipal Bonds
1.692%
1.813%
11/24/2021
10/01/2028
180,000.00
149,115.60
179,188.74
(30,073.14)
(811.26)
N/A
Cetera
Investment Services
Municipal Bonds
3.000%
1.942%
08/19/2019
O6/01/2029
115,000.00
103,997.95
125,961.80
(21,963.85)
10,961.80
N/A
Cetera
Investment Services
Municipal Bonds
4.000%
3.214%
03/22/2021
09/01/2031
60,000.00
56,109.00
64,292.00
(8,183.00)
4,292.00
09/01/2024
Cetera
Investment Services
Municipal Bonds
3.500%
2.699%
11/23/2021
02/01/2033
50,000.00
46,405.50
54,390.44
(7,984.94)
4,390.44
02/01/2025
Cetera
Investment Services
Municipal Bonds
3.250%
2.655%
08/13/2011
O6/01/2029
75,000.00
70,627.50
79,860.31
(9,232.81)
4,860.31
02/01/2025
Cetera
Investment Services
Municipal Bonds
3.1205
2.303%
11/23/2021
10/01/2034
50,000.00
44,799.00
54,773.69
(9,974.69)
4,773.69
04/01/2027
Cetera
Investment Services
Municipal Bonds
3.125%
2.456%
11/23/2021
02/01/2035
50,000.00
44,732.50
54,236.11
(9,503.61)
4:236.11
02/01/2026
Broker Total
50.8%
9,619,000.00
8,990,051.58
9,967,822.04
(979,551.25)
348,822.04
TOTAL INVESTMENTS 100.0%
9/30/2022
% of
8/31/2022
% of
Monthly
Maturity
Current Value
Product Type
Total Value
Total
Total Value
Total
Change
Less than 1 year
$4,672,657.20
26.4%
ME Money Market
$21,988.65
0.1%
$37,558.30
0.2%
($15,569.65)
1-2years
2,006,795.05
11.3%
CD's
3,191,359.36
18.0%
3,261,783.07
17.9%
(70,423.71)
2-3years
2,504,835.54
14.2%
Government Bonds
5,498,576.00
31.1%
5,540,862.85
30.4%
(42,286.85)
3-4years
4,389,324.41
24.8%
,.: Municipal Bonds
8,988,270.79
50.8%
9,381,810.56
51.5%
393,539.77
4-5years
2,339,512.10
13.2%
TOTAL
$17,700,194.80
100.0% $18,222,014.78
100.0%
$521,819.98
5+years
1,787,070.50
10.1%
TOTAL
$17,700,194.80
100.0%
Municipal Bonds
Money Market
$5000,000.00
50.8°/
0.1%
CD's
4
$4 672 657
•.
�18.0%
$4,500,000.00 "...
$4,000,000.00
$3,500,000.00
$3,000,000.00 ...
$2 504 836
$2 339 512
$2,000,000.00
$2 006 795
$1,500,000.00
--
---
-
--
$500,000.00...::::
$0.00
Less than 1-2years
2-3years 3-4years 4-5years 5+years
Government
Bonds
year
31.1%
ELECTRIC DIVISION
Operating Revenue
September 2022
CLASS
AMOUNT
KWH
/KWH
Street Lights
$21.09
387
$0.05450
Electric Residential Service
$461,582.10
4,247,602
$0.10867
All Electric Residential Service
$15,365.24
128,710
$0.11938
Electric Small General Service
$149,981.95
1,441,078
$0.10408
Electric Large General Service
$659,493.21
7,150,180
$0.09223
Electric Large Industrial Service
$760,004.11
9,099,000
$0.08353
Total
$2,046,447.70
22,066,957
$0.09274
Power Adjustment $0.00455
Rate Without Power Adjustment $0.08819
Electric Division Year -to -Date
M2022$A--t 02021$A--t ■2022KWH110 02021 KWH110
24,000,000
23,000,000
22,000,000
21,000,000
20,000,000
19,000,000
18,000,000
17,000,000
16,000,000
15,000,000
14,000,000
13,000,000
12,000,000
11,000,000
10,000,000
9,000,000
8,000,000
7,000,000
6,000,000
5,000,000
4,000,000
3,000,000
2,000,000
1,000,000
0
Street Lights Residential All Elec. Small Gen. Large Gen. Large For Resale Total
Resid. Srv. Srv. Industrial
NOTE: Sales for resale includes capacity sales and market sales.
NATURAL GAS DIVISION
Operating Revenue
SEPTEMBER 2022
CLASS
AMOUNT
MCF
/$ MCF
Residential
$144,645.30
7,743
$18.68078
Commercial
$108,901.86
8,950
$12.16781
Large Industrial
$33,170.15
4,013
$8.26567
Large Industrial Contracts
$276,466.99
43,972
$6.28734
Total
$563,184.30
64,678
$8.70751
® 2022 $ Amount
11,000,000
10,000,000
9,000,000
8,000,000
7,000,000
6,000,000
5,000,000
4,000,000
3,000,000
2,000,000
1,000,000
0
Fuel Adjustment $0.00000
Rate Without Fuel Adjustment $8.70751
Natural Gas Division Year -to -Date
0 2021 $ Amouni ■ 2022 MCF 132021 MCF
Gas Residential Gas Commercial Large Industrial Large Industrial Total
Contracts
Monthly Report -
Hutchinson Utilities
Commission
Hutchinson Utilities
Commission
Year
Minimum duration Substation
2022
5 -----
Month
Maximum duration Circuit
09 - September
v -----
Annual Report?
Top-level Cause Remove Major Events?
0 Yes
----- ".. -----
(*' No
v
IEEE 1366 Statistics
Metric
Sep 2022
Sep 2021
SAIDI
1.952
0.031
SAIFI
0.0149
0.00056
CAI DI
131
56.999
ASAI
99.9953 %
99.9999
Momentary Interruptions
0
0
Sustained Interruptions
1
1
Circuit Ranking - Worst Performing
Ranked by Outage Count
Circuit Substation NumberofOutages
1=dr#16 Plant 1 1
Ranked by Customer Interruptions
Circuit Substation Customer Interruptions
1=dr#16 Plant 1 111
Ranked by Customer Minutes of Duration
Circuit Substation Customer Minutes of Duration
1=dr#16 Plant 1 14,541
Historical Monthly SAIDI Chart
SAIDI
of monthly SAIDI values
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2021 2021 2021 2022 2022 2022 2022 2022 2022 2022 2022 2022
Historical Monthly SAIFI Chart
SAIFI
of monthly SAIFI values
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2021 2021 2021 2022 2022 2022 2022 2022 2022 2022 2022 2022
Causes Ranked by Count
Cause
Underground
Causes Ranked by Duration
Cause
Count
Duration
Underground 14,541
Top 1 Outages for the Month
Customers
Address Interrupted
Merrill and 111
Linden
Total Customers Affected for the Month:
Average Customers Affected per Outage:
Customer Minutes of
Duration Interruption Start Date
131 14,541 09/17/2022
111
ME
Work
Order Desc�ri tio_n
12201 Plant 1 Asphalt Parking Lot
12202 Control Room A/C
12203 Plant 2 Air Dryer
12204 Cooling Tower Repairs
12205 Power Plant Exhaust Fan and Controls
12206 Plant 2 Unilux Boiler
Electric Production
Total
Total
Materials
Labor
R d eted
Actual
Difference
$ 150,000.00 $
-
$ 150,000.00
$ 120,543.00
$
(29,457.00)
16,000.00
3,000.00
19,000.00
12,130.32
(6,869.68)
16,000.00
3,000.00
$ 19,000.00
29,705.92
$
10,705.92
175,000.00
-
$ 175,000.00
19,080.15
$
(155,919.85)
19,000.00
2,000.00
$ 21,000.00
36,275.84
$
15,275.84
-
_.
$
42,567.00
$
42,567.00
$ 376,000.00 $
8,000.00
$ 384,000.00
$ 260,302.23
$
(123,697.77)
Work
Order
Descri�ation
22103
Feeders 15 & 16 Reconductor
22201
Pole Repair and Replacement
22202
Hutch Sub SCADA
22203
Plant 1 Sub SCADA Relays
22204
3M Sub SCADA
22205
Station Equipment
22206
Right of Way Clearing
22207
Install Duct
22208
Feederl2A Reconductor
22209
Civil Air Patrol
22210
City Road Projects
22211
New Developments
22212
Feederl2A Reconductor
22213
EV Charging Station Transformer
22214
Transformer Replacements
22215
Transformer New Developments
22216
Meters
22217
LED Conversion
Electric Distribution
Materials
Labor
$ 35,000.00
$ 75,000.00
15,000.00
-
125,000.00
-
80,000.00
16,000.00
40,000.00
5,000.00
10,000.00
-
15,000.00
30,000.00
7,000.00
10,000.00
50,000.00
15,000.00
10,000.00
40,000.00
50,000.00
30,000.00
175,000.00
$ 737,000.00
65,000.00
20,000.00
2,000.00
10,000.00
7,000.00
1,000.00
14,000.00
35,000.00
$ 250,000.00
Total
Total
Bud ted
Actual
Difference
$ 110,000.00
$ 28,008.44
$
(81,991.56)
15,000.00
-
$
(15,000.00)
125,000.00
-
$
(125,000.00)
96,000.00
156,248.37
$
60,248.37
45,000.00
22,181.00
$
(22,819.00)
10,000.00
719.82
$
(9,280.18)
80,000.00
113,642.28
$
33,642.28
50,000.00
107,858.20
$
57,858.20
9,000.00
1,956.91
$
(7,043.09)
20,000.00
22,494.62
$
2,494.62
50,000.00
52,496.38
$
2,496.38
22,000.00
8,086.38
$
(13,913.62)
11,000.00
-
$
(11,000.00)
54,000.00
-
$
(54,000.00)
50,000.00
24,096.05
$
(25,903.95)
30,000.00
13,586.58
$
(16,413.42)
210,000.00
184,937.73
$
(25,062.27)
$ 987,000.00
$ 736,312.76
$
(250,687.24)
Work Order
Descri t ion
52103
Natural Gas Service Truck
52201
EV Fast Charger
52202
EV Level 2 Charger
52203
Replace #037 Dump Truck
52204
Replace #130
52205
Replace #948
52206
Paint Booth
Administrative
Total
Total
Budgeted
Actual Difference
$ 72,000.00
$ 14,527.35 $ 57,472.65
60,000.00
- 60,000.00
10,000.00
- 10,000.00
66,950.00
- 66,950.00
75,190.00
- 75,190.00
75,190.00
- 75,190.00
2,000.00
- 2,000.00 '
$ 361,330.00 $ 14,527.35 $ (346,802.65)
Natural Gas
Work
Total
Total
Order
Description
Materials
Labor
Budgeted
Actual
Difference
62109
Isolated Main Replacement (Btn Barley & Gler $
27,500.00
$ 5,000.00
$ 32,500.00 $
4,389.17
$ (28,110.83)
62201
2 12" Valves, Vacuum Purging, Pigging Lat Linf
800,000.00
5,000.00
805,000.00
179,947.44
(625,052.56)
62202
Specific Gravity Meter
50,000.00
500.00
50,500.00
-
(50,500.00)
62203
Pipeline Satellite Imagery
26,500.00
1,000.00
27,500.00
21,630.00
(5,870.00)
62204
Misc Developments and System Improvemeni
50,000.00
10,000.00
60,000.00
11,667.44
(48,332.56)
62205
City Projects
15,000.00
6,500.00
21,500.00
27,030.13
5,530.13
62206
50 psig Improvement Project -Distribution
520,000.00
5,000.00
525,000.00
-
(525,000.00)
62207
Regulator Station Improvements
20,000.00
5,000.00
25,000.00
-
(25,000.00)
62208
50 psig Improvement Project- DRS
230,000.00
1,000.00
231,000.00
-
(231,000.00)
62209
Service Lines
57,000.00
35,000.00
92,000.00
53,254.16
(38,745.84)
62210
Meters, AMI, and All Fittings
150,000.00
4,000.00
154,000.00
48,921.86
(105,078.14)
62211
Residential Regulators
9,000.00
-
9,000.00
-
(9,000.00)
62212
Industrial Metering and Regulation
20,000.00
3,500.00
23,500.00
8,747.49
(14,752.51)
62213
CP AMI Monitors, AMI Pressure Monitors
50,000.00
3,000.00
53,000.00
10,942.51
(42,057.49)
$ 2,025,000.00 $ 84,500.00 $ 2,109,500.00 $ 366,530.20 $ (1,742,969.80)
,c��,«
HUTCHINSON UTILITIES COMMISSION
Board Action Form
f tit
W
Agenda Item: Review Policies
Presenter: Angie Radke
Agenda Item Type:
Time Requested (Minutes): 5
Review Policies
Attachments: Yes
BACKGROUND/EXPLANATION OFAGENDA ITEM:
As part of HUC's standard operating procedures, a continual policy review is practiced.
This month, the following policies were reviewed and no changes are recommended on
these policies at this time:
i. Electric - Rate Schedule
ii. Security Light Rental — Rate to Furnish and Maintain Fixture
iii. Electric Service Requirements & Charges
iv. Temporary Service- Electric
v. Temporary Service in Case of Underground Failure
vi. Sealing of Meters — Electric
vii. Meter Testing - Electric
viii. Right -of -Way Clearing
ix. Tree Removal of Trimming
x. Locating Customer's Underground Utilities — Electric
A. Natural Gas - Rate Schedule
xii. Natural Gas Service Requirements & Charges
xiii. Temporary Service — Natural Gas
xiv. Natural Gas Meter Requirements & Placement
xv. Meter Testing — Natural Gas
xvi. Natural Gas Service Work
xvii. Locating Customer's Underground Utilities — Natural Gas
BOARD ACTION REQUESTED:
None
Fiscal Impact:
Included in current budget: ; BudgetChange:
PROJECTSECTION:
Total Project Cost: Remaining Cost:
SERVICE POLICIES - ELECTRIC
Rate Schedule
Electric Residential Service Code 10 —Available for domestic purposes only, in a single
or multiple residence. All newly connected multiple dwelling units shall have one meter
per unit, and a house meter.
Energy charge: 7.852 cents per KWH
Meter charge: $16.90 per meter
Electric Small General Service Code 30 — Applicable to any customer for single or three
phase electric service with less than 50 KW demand supplied through one meter at the
secondary voltage at that location. At any time the customer demand reaches 50 kilowatts
for three consecutive months, the customer will be removed from the Electric Small
General Service rate and billed under Electric Large General Service rate.
Energy charge:
First 2000 KWH per month --- 8.994 cents per KWH
Over 2000 KWH per month --- 8.078 cents per KWH
Monthly Customer Charge: $21.60
Electric Large General Service Code 40 Code 41 — Applicable to any customer for
combined power and lighting with a minimum demand of 50 kilowatts for single or three
phase electric service supplied through one meter at the secondary voltage at that
location. If demand drops below 50 kilowatts for 12 consecutive months, the customer will
be removed from Electric Large General Service rate and billed under Electric Small
General Service.
Demand charge: $10.00 per KW
Energy charge: 5.783 cents per KWH
Monthly Customer Charge $107.60
Minimum monthly charge: 75% of the maximum demand charge —the maximum demand
is the customer's peak usage over the previous 12 months.
SERVICE AT PRIMARY VOLTAGE: Customer owns/maintains facilities, and service
provided at primary voltage — a 5% discount will be applied to the energy charge. This
adjustment includes a discount for primary metering.
HUC owns/maintains facilities, and service provided at primary voltage — a 2% discount
will be applied to the energy charge.
POWER FACTOR PENALTY: A power factor penalty will apply if the customers
measured power factor drops below .94.
Large Industrial Service Code 50 and 51 — Applicable to any customer for combined
power and lighting with a minimum demand over 4000 KW during any one month in a 12
month period. Service will be delivered at the primary voltage available at the customer's
property line. The customer will own and maintain all electrical facilities on the customer's
side of the metering transformer.
Demand Charge:
Energy Charge:
Monthly Customer Charge
$11.00 per KVA
5.274 cents per KWH
$300.80
Power Cost Adjustment - Power cost adjustment is based on the combined costs of
purchased power from outside suppliers, fuel (natural gas and fuel oil), and unrecovered
or excess revenues from previous month.
Computations of power adjustments shall be made monthly. The resultant adjustment, if
any, shall be applicable for the month.
2
Security Light Rental — Rate to Furnish and Maintain Fixture
HIGH PRESSURE SODIUM
Monthly Monthly
Lamp Size Charge Lamp Size Charge
150 watt metered $3.00 150 watt unmetered $ 7.00
250 watt metered $3.50 250 watt unmetered $10.00
Lights will be dusk to dawn type with photo control and will be installed on existing pole
in the area. If a new pole is needed, customer will pay for the pole and installation.
All new installations will be High Pressure Sodium.
All rates subject to power cost adjustment.
Electric Service Requirements and Charges
HUC will require a 24-hour notice, a copy of the State Board of Electricity Certificate of
Inspection, and an established account prior to installing a meter and making the final
connection.
HUC shall not install any facilities until all affected properties are within 6 inches of final
grade.
Installation of Anv Electric Services — November 1 Throuah March 31
The final determination on installation of electric services shall be made by HUC.
New Single -Family Dwelling — Service Size: 200 Amperes or less
Single-family dwelling customers will be 240/120 volt single-phase service.
HUC shall furnish and install the underground conductors to serve the single-family home
with a one-year warranty after installation date. The underground service is the property
of the homeowner at date of installation.
(4/0-2/0-4/0 URD): Minimum $300.00 Installation Charge up to 100 ft.; additional
$2.00/ft. in excess of 100 ft.
The customer or their contractor shall provide and install a 200A, ringless meter socket
with lever bypass (See meter requirement/placement section).
New Single -Family Dwelling — Service Size: Greater than 200 Amperes
Single-family dwelling customers will be 240/120 volt single-phase service.
Current transformer metering is required. HUC shall furnish the current transformers,
meter socket and meter (See meter requirement/placement section). The customer or
their contractor shall provide the current transformer housing and facilities, install the
current transformers, mount the meter socket and provide an empty 1-Y4 inch conduit to
the meter socket. HUC shall install the meter wiring and meter. No current transformer
metering will be allowed in the power transformer secondary compartment.
Bar type current transformers will be used. Provisions for voltage connections for the
meter must also be provided.
The customer will be responsible for installing the service to the utility transformer or
pedestal location. HUC will be responsible to make all secondary connections in the
transformer. Transformer secondary connections will be limited to a maximum of four
conductors per phase with a maximum size of 750 MCM per conductor. If additional
conductors are required per phase, the owner or contractor must provide an approved
secondary transition cabinet. HUC's Electric Division may be contacted for further details.
E
New Multi -Family Dwelling, Commercial, or Industrial
The customer will be responsible for installing the service to the utility transformer or
pedestal location. For any services that require current transformer metering, the
customer will be responsible to install the conductor from the metering cabinet to the
transformer. For any three-phase services, the customer shall furnish the transformer pad
and ground grid. The transformer location shall be determined by HUC.
HUC will provide the following voltages:
120/208 volts three phase, not to exceed 3,000 amperes without prior approval.
277/480 volts three phase, not to exceed 3,000 amperes without prior approval.
7,970/13,800 volts three phase, with prior arrangements with HUC.
HUC will be responsible to make all secondary connections in the transformer.
Transformer secondary connections will be limited to a maximum of four conductors per
phase with a maximum size of 750 MCM per conductor. If additional conductors are
required per phase, the owner or contractor must provide an approved secondary
transition cabinet. HUC's Electric Division may be contacted for further details.
On services greater than 200 amperes at 240/120volts, current transformer metering is
required. HUC shall furnish the current transformers, meter socket and meter. The
customer or their contractor shall provide the current transformer housing and facilities,
install the current transformers, mount the meter socket and provide an empty 1-Y4 inch
conduit to the meter socket. HUC shall install the meter wiring and meter. No current
transformer metering will be allowed in the power transformer secondary compartment.
Any service greater than 240 volts, shall require current transformer metering.
Bar type current transformers will be used. Provisions for voltage connections for the
meter must also be provided. Approved multi -family dwelling meter stacks will be provided
by the customer or their contractor.
Primary metering at 7,970/13,800 volts will be by special arrangement and approval of
HUC.
G
Temporary Service
For temporary service, please contact HUC's Customer Service Department.
HUC shall bill the customer or their contractor for all related expenses.
Temporary Service in Case of Underground Failure
When an underground service fails, HUC will furnish a temporary service to the customer
at no charge. The customer will have ten working days to repair or replace the service.
In the event the work can't be completed within ten working days the customer may
contact HUC to perform the required maintenance at HUC's current time and material
rates. If after ten working days, the required maintenance has not been completed or
the customer has not contacted HUC to make arrangements to have the service repaired,
HUC will remove the temporary service.
In the event of frost, the customer will need to contact HUC to make arrangements to
have the repair done at a later date.
7
Electric Meter Placement
HUC reserves the right to specify the electric meter location on all installations.
Electric service lines and meter housing are the property of the home/business owner.
No customer owned device or equipment is allowed to be connected to the meter socket.
Meters may be relocated to a location agreed upon by HUC and the customer (or location
approved by HUC.). The customer will be responsible for all costs involved in relocating
these facilities.
All meters must be located on an external wall. New construction electric meters must be
located within 10 feet of the natural gas meter if HUC is providing both services.
Electric meters shall be accessible at all times for disconnection, examination, reading,
replacement or necessary maintenance. Electric meters not accessible are subject to
disconnection and will need to be moved to a location approved by HUC, at the
home/business owner's expense.
HUC requires a minimum of a 3-foot clear zone in front of the electric meter.
Reasonable care must be taken to protect all metering facilities when remodeling,
residing, roofing, painting, etc. In the event of damage to the electric facilities, the
customer shall be responsible for the cost of repairing or replacing the electric facilities.
Conditions may exist which may require other restrictions or distances (e.g. multiple
meters or commercial/industrial).
Any exceptions require the approval of HUC prior to the start of construction. If
violations or deviations are determined, the customer will be responsible for the
cost of the correction.
Single Family Dwellings
All residential electric metering facilities shall be located on the side of the home within 6
feet of the front building wall and 60 inches from finished grade. Front building wall is
defined as the wall nearest the street of the resident's living space.
Multi -Family Dwellings/Multiple Business Establishments
All HUC electric meters must be located on the exterior wall of the building. Individual
metering is required for each single-family private residence contained in a multi -family
dwelling and each separately owned and/or operated business. In addition, if required, a
"house meter" shall also be installed in these establishments.
Commercial or Industrial
All commercial and industrial electric meters must be located outside. If remodeling is
done on the premises, which would cause the meter to be located inside, the owner, at
owner's expense, must relocate the meter to the outside to a location agreed upon (or
approved by) by HUC.
Sealing of Meters
Electric meters and current transformer housings, which have been sealed by HUC, shall
not be broken or tampered with without the consent of HUC except in emergency cases.
HUC shall be notified immediately after a seal has been broken. If HUC is not notified and
HUC personnel discover a broken seal, a $10 broken seal charge may be assessed to
the customer.
Seals will be assigned to each meter/account by color according to the following:
Gray Seal
Red Seal
Blue Seal
Yellow Seal
Regular Account
Meter Disconnected for Non -Payment
Meter Disconnected by Customer Request
Life Support Equipment
9
Meter Testing
HUC will test all meters periodically for accuracy and mechanical condition. All electric
meters must be accurate to within 2%, plus or minus, at full and light load. Upon request
of the customer, HUC will test the accuracy of an electric meter. If the meter is found to
be registering more than 2% fast, there will be no testing charge to the customer. If the
meter is found to be accurate within the 2% limit, a $40 trip charge will be billed to the
customer. HUC has the right to place special meters on the premises of a customer for
the purpose of testing all or part of the customer's load at no expense to the customer.
10
Right -of -Way Clearing
HUC shall maintain right-of-way clearance on all overhead and underground facilities.
11
Tree Removal or Trimming
Tree removal or trimming for other than right-of-way clearance is the responsibility of the
property owner. Please notify HUC with any questions concerning tree removal or
trimming.
Any repair of damage to the HUC electrical distribution system caused by tree removal or
trimming, by the property owner or their representatives will be billed to the property
owner.
12
Locating Customer's Underground Utilities
HUC will locate all underground electric distribution and transmission facilities up to the
meter at no charge to the customer or landowner.
13
SERVICE POLICIES - NATURAL GAS
Rate Schedule
Residential Code 60 — Available to any customer who uses less than 70 MCF of gas
per day.
Energy Charge: $7.4040 per MCF, or $.0074040 per CF
Meter Charge: $16.10 per meter
Commercial Gas Code 65 — Available to any customer who uses less than 200 MCF of
gas per day.
Energy charge: $7.9682 per MCF, $.0079682 per CF
Meter charge: $64.70 per meter
Large Industrial Gas Code 89 Code 91 — Available to all customers who use in excess
of 200 MCF of gas per day. The demand level shall be based on the maximum daily
volume (MCF per day) of natural gas delivered to the customer per month.
Monthly Demand Charge per
MCF of Billing Demand
$8.00 per MCF
Monthly Customer Charge: $285.00
Energy Charge of
Gas per MCF Delivered
$7.5450 per MCF, or $.0075450 per CF
Minimum Monthly Charge: The demand charge for month.
Fuel Cost Adjustment — Fuel cost adjustment is based on the combined cost of
purchased gas and unrecovered or excess revenues from previous month.
Computations of fuel adjustment shall be made monthly. The resulting adjustment, if any,
shall be applicable for the month.
All rates are subject to fuel cost adjustment.
14
Natural Gas Service Requirements and Charges
HUC shall not install any facilities until all affected properties are within 6 inches of final
grade.
HUC shall furnish and install the underground natural gas service line. The service line to
the meter shall remain the property of HUC.
Type/Size
Fee
Single-family residential - 3/4" IPS
$300 — up to 150 ft. plus
$2.00/ft. in excess of 150 ft.
Multi-family/Commercial/Industrial - 3/4" IPS
$750 — up to 100 ft. plus
$5.00/ft. in excess of 100 ft.
Multi-family/Commercial/Industrial — 2" IPS
$1500 — up to 100 ft. plus
$5.00/ft. in excess of 100 ft.
Industrial — 4" IPS and larger
Time and Material Expense
Service line length is defined as "distance from customer's property line to metering
facilities", or in the instance the distribution main is located in rear easement, "distribution
main to metering facilities".
No structure or building may be located over natural gas lines or metering facilities. Ir
the event that a structure or building is determined to be located over natural gas facilities,
the natural gas facility must be relocated to a mutually agreed upon location. The
customer shall be responsible for all costs associated with the relocation.
No service line valve or any portion of the natural gas metering facilities may be buried.
The customer shall be responsible for all costs incurred in raising all facilities.
Hutchinson Utilities Commission shall begin installing excess flow valves, as of April 14,
2017, on all newly installed and replacement service lines serving the following types of
services before the line is activated:
A single service line to one single-family residence;
A branched service line to a single-family residence installed concurrently
with the primary single-family residence service line (i.e., a single EFV
may be installed to protect both service lines);
A branched service line to a single-family residence installed off a
previously installed single-family residence service line that does not
contain an EFV;
15
• Multifamily residences with known customer loads not exceeding 1,000
SCFH per service, at time of service installation based on installed meter
capacity, and
• A single, small commercial customer served by a single service line with a
known customer load not exceeding 1,000 SCFH, at the time of meter
installation, based on installed meter capacity.
Hutchinson Utilities shall install either a manual service line shut-off valve or, if possible,
based on sound engineering analysis and availability, an excess flow valve for any new
or replaced service line with installed meter capacity exceeding 1,000 SCFH.
All new natural gas consumer -owned fuel lines, downstream of the metering facilities,
must be pressure tested, prior to the gas meter being set. The test must be verified by
an approved inspector.
Installation of Natural Gas Service Lines — November 1 through March 31
Final determination on installation of natural gas service lines shall be made by HUC.
16
Temporary Service
HUC does not offer temporary natural gas service.
17
Natural Gas Meter Requirements and Placement
HUC shall furnish and install the natural gas meter at no charge to the customer.
HUC reserves the right to specify the natural gas meter location on all installations.
All meters must be located on an external wall of the building, at a horizontal distance of
no less than 3 feet from fresh air intakes, windows or door openings. New construction
natural gas meters must be located within 10 feet of the electric meter if HUC is providing
both services.
Access to all natural gas meters shall not be obstructed.
Natural gas meters shall be located in ventilated spaces readily accessible for
examination, reading, replacement or necessary maintenance. Decks, porches, etc. shall
not be constructed over a natural gas meter.
Natural gas meters shall not be located where they will be subject to damage, such as
adjacent to a driveway or other locations subject to vehicular traffic, in public passages,
where they will be subject to excessive corrosion or vibration or in areas subject to ice
and snow damage.
Natural gas meters shall not be installed directly beneath external stairways.
Natural gas meters shall not be located where they will be subjected to extreme
temperatures or sudden extreme temperature changes (e.g., air ducts, dryer vents).
Manufacturer's installation specifications shall be adhered to when installing fresh air
intake and exhaust terminations near natural gas metering facilities.
Natural gas regulators shall be located - no less than 3 feet from any source of ignition or
any source of heat that may damage the facilities.
HUC requires a minimum of a 3-foot clear zone in front of the natural gas meter.
Reasonable care must be taken to protect all metering facilities when remodeling, roofing,
painting, etc. In the event of damage to the natural gas facilities, the customer shall be
responsible for the cost of repairing or replacing the natural gas facilities.
Conditions may exist which may require additional restrictions or distances (e.g. multiple
meters, etc.). Please contact HUC if you should have any questions regarding your
natural gas metering facilities.
Modifications made to the customer's metering facilities, necessitated by customer
changes, shall be performed by HUC, at the customer's expense.
All natural gas service lines retired due to building demolition, overbuilding, etc. shall be
im
retired at the customer's expense. HUC Natural Gas Division performs all retirement
work on natural gas facilities. Estimate is provided by HUC Natural Gas Division when
requested.
All exceptions require the approval of HUC prior to the start of construction. If
violations or deviations are determined, the customer shall be responsible for the
cost of the correction.
Single Family Dwellings
HUC shall provide natural gas to residential customers at the standard delivery pressure
of 7 inches of water column, measured at the inlet to the natural gas meter.
All residential natural gas metering facilities shall be located on the side of the home within
6 feet of the front building wall. Front building wall is defined as the wall nearest the street
of the resident's living space.
Multi -Family Dwellings/Multiple Business Establishments
Delivery pressures greater than 7 inches of water column, for multi -family and multiple
business establishments, shall only be allowed by the prior approval of HUC. The
customer must provide adequate over -pressure protection for all fuel lines subject to
increased delivery pressure.
The single metering of multiple -family dwellings, apartment buildings or multiple business
establishments within a single building is permitted to the extent that each building is
centrally heated. Individual metering is required for all individually heated, single-family
private residences and each separately heated, owned and/or operated business.
Please contact HUC for specifications regarding meter facilities.
Commercial/Industrial Facilities
Delivery pressures greater than 7 inches of water column, for commercial and industrial
applications, shall only be allowed by the prior approval of HUC. The customer must
provide adequate over -pressure protection for all fuel lines subject to increased delivery
pressure.
Please contact HUC for specifications regarding meter facilities.
19
Meter Testing
HUC shall periodically test all natural gas meters for accuracy and sound mechanical
condition. Meters that have an average intest accuracy of 100, ± 2%, shall be considered
accurate. Average accuracy is defined as the average of the open and check flow
accuracies.
Accounts for which the natural gas meter tests in excess of 102% are subject to a refund.
This refund shall be based on the "as found average meter accuracy" and the customer's
consumption for the previous six month period.
Upon request of the customer, HUC shall test the average accuracy of the natural gas
meter. A $40 trip charge may be assessed to all accounts in which the "as found average
meter accuracy" is determined to be 102% or less.
20
Natural Gas Service Work
HUC personnel shall perform leak investigation and carbon monoxide testing at no charge
to the customer. HUC does not perform service work on customer owned facilities.
21
Locating Customer's Underground Utilities
HUC shall locate all natural gas underground distribution and transmission facilities up to
the meter at no charge to the customer or landowner.
22
HUTCHINSON UTILITIES COMMISSION
Board Action Form
Agenda Item: Approve Policy Changes
Jared Ma
Changes to Policies
BACKGROUND/EXPLANATION OFAGENDA ITEM:
As part of HUC's standard operating procedures, a continual policy review is
practiced. The following revisions to the policies below are recommended.
Disconnection of Residential Services by HUC
Disconnection of Commercial Services by HUC
BOARD ACTION REQUESTED:
Approve Policy Changes
Disconnection of Residential Services by HUC
1. Residential utility service may be disconnected for any of the following reasons:
• Failure to pay by the deadline on a delinquent account or failure to comply with the
terms of the budget payment plan.
• Failure to contact HUC to gain protection from disconnection under the Cold
Weather Rule.
• Failure to maintain the payment agreement established under the Cold Weather
Rule.
• Failure to comply with deposit requirement.
• Failure to pay for merchandise or charges for non -utility service billed by HUC.
• Payment of bill with a dishonored check.
• Failure to provide authorized utility personnel access to utility equipment.
• HUC shall disconnect residential utility service, without notice, where service has
been reconnected without HUC's authorization.
• HUC shall disconnect residential utility service, without notice, where it has
reasonable evidence that utility service is being obtained by potentially unsafe
devices or potentially unsafe methods that stop or interfere with the proper
metering of the utility service.
• HUC may disconnect residential utility service, without notice, where a dangerous
condition exists for as long as the condition exists.
• At the request of the property owner, as long as it's currently in owner's name < it d
no I~eir°u< it t occupies Iproperty,
• At the request of the realtor/bank, as long as it's currently in their name.
• If an account owner or property owner does not notify us, within three (3) business
days following disconnection of service for non-payment, a final bill will be
processed and the account will be closed.
2. HUC must have a Landlord Agreement on file acknowledging that landlord/owner will
be responsible for all utility charges after the read-out date requested by a tenant.
Failure of the landlord/owner to execute this form will lead to a shut off of services on
the read-out date requested from tenant.
3. For all items mentioned in number 1 and 2 above, a disconnect/reconnect fee shall be
applied. The disconnect/reconnect fee is as follows:
• A $40 trip charge to disconnect.
• A $40 trip charge to reconnect, payment shall be made with cash, money order or
credit card during regular business hours.
• After hours reconnection will follow the After Hours Reconnection Policy.
4. In the event that the customer pays after the deadline given on the disconnect letter,
and the payment is processed before physical disconnection, a $40 Removal from
Disconnect List Fee will be applied to their account.
5. If a realtor/bank requests to have service reconnected for one day in order to perform
an inspection, a $40 trip charge to reconnect and a $40 disconnect charge will be
applied.
6. In the event of unauthorized use of, or tampering with the equipment of HUC, a
tampering charge of $100 will be assessed to the customer's account. The appropriate
law enforcement agency will be notified. HUC reserves the right to charge the
customer for the cost of repairs to the equipment of HUC.
7. A dishonored payment will be assessed a $30 processing fee.
8. A dishonored payment to avoid disconnection, or to get reconnected, will be assessed
a $30 processing fee; plus:
• A $40 trip charge to deliver a door hanger, giving customer 24 hours to make
payment good with cash, money order or credit card.
9. HUC is not required to furnish residential service under conditions requiring operation
in parallel with Backup generating equipment connected to the customer's system if
such operation is hazardous or may interfere with its own operations or service to
other customers or operation as a condition or rendering service under such
circumstances.
FAILURE TO RESPOND TO THE DISCONNECT NOTICE SET FORTH ON THE BILL
OR FAILURE TO PAY FOR SERVICES RENDERED BY HUC MAY RESULT IN THE
DISCONNECTION OF SERVICES TO THE PROPERTY WITHOUT ANY ADDITIONAL
NOTICE TO THE CUSTOMER. IT IS THE CUSTOMER'S RESPONSIBILITY TO PAY
FOR SERVICES RENDERED AND TO ADVISE HUC OF ANY CHANGE IN ADDRESS.
NEITHER HUC NOR THE CITY OF HUTCHINSON, NOR ANY OF THE AGENTS,
EMPLOYEES OR REPRESENTATIVES OF THE CITY OF HUTCHINSON OR HUC,
WILL BE RESPONSIBLE FOR ANY DAMAGES OR CLAIMS INCURRED AS A RESULT
OF THE DISCONNECTION OF SERVICES.
Residential utility service may not be disconnected or refused for any of the following
reasons:
• Delinquency in payment for services by a previous occupant of the premises to be
served.
• Failure to pay for a different rate classification of utility service.
• Failure to pay the account of another customer as guarantor thereof.
• Failure to pay charges arising from any underbilling occurring more than 1 year
prior to the current billing and due to any misapplication of rates or faulty metering.
• If a customer is on the Budget Payment Plan and has a credit balance on account.
• 1weir°u< it t Ipays cuir°ir°eir t imoir°uI~lh o in < ccouir t llin Ilaind1lord's ir°u< im e,
Disconnection of Commercial Services by HUC
1. Commercial utility service may be disconnected for any of the following reasons:
• Failure to pay by the deadline on a delinquent account.
• Failure to comply with deposit requirement.
• Failure to pay for merchandise or charges for non -utility service billed by HUC.
• Payment of bill with a dishonored check.
• Failure to provide authorized HUC personnel access to utility equipment.
• HUC shall disconnect commercial utility service, without notice, where service has
been reconnected without HUC's authorization.
• HUC shall disconnect commercial utility service, without notice, where it has
reasonable evidence that utility service is being obtained by potentially unsafe
devices or potentially unsafe methods that stop or interfere with the proper
metering of the utility service.
• HUC may disconnect commercial utility service, without notice, where a dangerous
condition exists for as long as the condition exists.
• At the request of the property owner, as long as it's currently in owner's name < it d
no I~eir°u< it t occupies Iproperty,
• At the request of the realtor/bank, as long as it's currently in their name.
2. HUC must have a Landlord Agreement on file acknowledging that landlord/owner will
be responsible for all utility charges after the read-out date requested by a tenant.
Failure of the landlord/owner to execute this form will lead to a shut off of services on
the read-out date requested from tenant.
3. For all items mentioned in number 1 and 2 above, a disconnect/reconnect fee shall be
applied. The disconnect/reconnect fee is as follows:
• A $40 trip charge to disconnect.
• A $40 trip charge to reconnect, payment shall be made with cash, money order or
credit card during regular business hours.
• After hours reconnection will follow the After Hours Reconnection Policy.
4. In the event that the customer pays after the deadline given on the disconnect letter,
and the payment is processed before physical disconnection, a $40 Removal from
Disconnect List Fee will be applied to their account.
5. If a realtor/bank requests to have service reconnected for one day in order to perform
an inspection, a $40 trip charge to reconnect and a $40 disconnect charge will be
applied.
6. In the event of unauthorized use of, or tampering with the equipment of HUC, a
tampering charge of $100 will be assessed to the customer's account. The appropriate
law enforcement agency will be notified. HUC reserves the right to charge the
customer for the cost of repairs to the equipment of HUC.
7. A dishonored payment will be assessed a $30 processing fee.
8. A dishonored payment made to avoid disconnection, or to get reconnected, will be
assessed a $30 processing fee; plus:
• A $40 trip charge to deliver a door hanger, giving customer 24 hours to make
payment good with cash, money order or credit card.
9. HUC is not required to furnish commercial service under conditions requiring operation
in parallel with Backup generating equipment connected to the customer's system if
such operation is hazardous or may interfere with its own operations or service to
other customers or operation as a condition or rendering service under such
circumstances.
FAILURE TO RESPOND TO THE DISCONNECT NOTICE SET FORTH ON THE BILL
OR FAILURE TO PAY FOR SERVICES RENDERED BY HUC MAY RESULT IN THE
DISCONNECTION OF SERVICES TO THE PROPERTY WITHOUT ANY ADDITIONAL
NOTICE TO THE CUSTOMER. IT IS THE CUSTOMER'S RESPONSIBILITY TO PAY
FOR SERVICES RENDERED AND TO ADVISE HUC OF ANY CHANGE IN ADDRESS.
NEITHER HUC NOR THE CITY OF HUTCHINSON, NOR ANY OF THE AGENTS,
EMPLOYEES OR REPRESENTATIVES OF THE CITY OF HUTCHINSON OR HUC,
WILL BE RESPONSIBLE FOR ANY DAMAGES OR CLAIMS INCURRED AS A RESULT
OF THE DISCONNECTION OF SERVICES.
Commercial utility service may not be disconnected or refused for any of the following
reasons:
• Delinquency in payment for services by a previous occupant of the premises to be
served.
• Failure to pay for a different rate classification of utility service.
• Failure to pay the account of another customer as guarantor thereof.
• Failure to pay charges arising from any underbilling occurring more than 1 year
prior to the current billing and due to any misapplication of rates or faulty metering.
• 1weir°u< it t Ipays cuir°ir°eir t imoir°uI~lh o in < ccouir t llin Ilaind1lord's ir°u< im e,
���
HUTCHINSON UTILITIES COMMISSION
Board Action Form
.,b TIC$
Agenda Item: Approval of Rollover of Northern Natural Gas Transportation Contract No. 21279.
Presenter: John Webster
Agenda Item Type:
Time Requested (Minutes): 2
New Business
Attachments: Yes
BACKGROUND/EXPLANATION OFAGENDA ITEM:
Hutchinson Utilities maintains 100 Dth/day of capacity on the Northern Natural Gas
Company (NNG) transmission system. Maintaining capacity on the NNG system
provides for a secondary supply of natural gas to the City of Hutchinson in the event of a
catastrophic failure to the Hutchinson Utilities' natural gas transmission line.
BOARD ACTION REQUESTED:
Approval of rollover of Northern Natural Gas Contract No. 21279, Amendment No. 28
Fiscal Impact: $14,000
Included in current budget: Yes Budget Change:
PROJECT SECTION:
Total Project Cost: Remaining Cost:
4orthern
4Natural Gas.
A BERKSHME HATHAWAY ENERGY COMPANY
Northern Natural Gas Company
Amendment to TF Throughput Service Agreement
Date: 10/13/2022
Shipper Name: HUTCHINSON UTILITY COMMISSION
Contract No.: 21279 (Agreement)
Amendment No.: 28
WHEREAS, the entitlement m this Agreement expires 10/31/2023 and is subject to Grandfathered Rollover Rights; and
WHEREAS, Shipper desires to rollover this Agreement for five (5) years at the maximum tariff rates;
NOW THEREFORE, the Agreement is amended as follows:
1. The volume, term, and/or point provisions are amended as follows:
a. The term of the Agreement is extended through 10/31/2028.
b. The contract maximum daily quantities, primary receipt and delivery points, and terms are set forth on Appendices "A"
and "B."
c. The Appendices to the Agreement are deleted in their entirety and replaced with the Appendices "A" and "B" attached
hereto and incorporated herein by this reference. All references to Appendix "A" or Appendix "B" shall be deemed to refer to
the Appendices attached hereto.
2. The parties agree that a facsimile or other electronic version of this document, when properly executed and transmitted,
shall be considered for all purposes to be an original document, and shall be deemed for all purposes to be signed and
constitute a binding agreement. The entire agreement must be faxed or transmitted to Northern. Upon Northern's acceptance
and execution, an executed copy will be returned via FAX to the number appearing on the faxed offer or such other number
as directed or otherwise electronically transmitted.
3. This Agreement, as amended, constitutes the entire agreement between the parties with respect to the subject matter of
this Agreement and shall be binding upon and shall inure to the benefit of the parties hereto and their respective successors
and assigns. No promises, agreements or warranties additional to this Agreement other than as may be contained in
Northern's FERC Gas Tariff will be deemed to be a part of this Agreement nor will any alteration, amendment or
modification be effective unless confirmed in writing by the parties.
The effective date of this Amendment is 11/01/2023.
Except as amended herein, all provisions of the Agreement are hereby confirmed by the parties to be and remain in full force
and effect.
NORTHERN NATURAL GAS COMPANY HUTCHINSON UTILITY COMMISSION
By: eC oea .& By:
Title: VP, Customer Service and Bus Dev Title:
Date: 10/12/2022 Date:
9
O
O
O
y
0
M
I/
F+ F+
O O O O
w+ w+
O O O O
00 00f
00 00�'
a
0 0 0 oL
oI
o
a;
104
'
z
[o
N z
>
co
o
yn
�CA
o
o
0 0 0
0 0 0
ITI
0 o a
0 o a
w
0 0 0
r"
CrQ
0 0 0
w
rr rr
o
0 0 0
C
O
0 0 0
0 0 0
0 0 S
0 0 0
a
o
0
0
0
0 0 0
0 0 0
<
i�
CD
o
00
0 0 0
NJ
W
HUTCHINSON UTILITIES COMMISSION�
Board Action Form
Agenda Item: Approve 2022 Audit Services with Conway Deuth & Schmiesing
Presenter: Jared Martig
Agenda Item; Type:
Time Requested (Minutes): 2
New Business
Attachments: No
BACKGROUND/EXPLANATION OFAGENDA ITEM:
Audit services for fiscal year 2022 have increased over $25,000 so this will be the first
time it will need to be approved. Below is a history of audit fees.
2021: $24, 850
2020: $24, 750
2019. $24, 750
2018: $24, 750
2017: $23,200
2016: $22,750
2015: $22,525
2014. $21, 950
2013: $21, 950
2012: $21, 500
2011: $21,250
BOARD ACTION REQUESTED:
Approve fiscal year 2022 audit services with Conway Deuth & Schmiesing
Fiscal Impact: $26,000
Included in current budget: Yes Budget Change: No
PROJECT SECTION:
Total Project Cost: Remaining Cost:
HUTCHINSON UTILITIES COMMISSION�
Board Action Form
Agenda Item: Digger Derrick Repair
Presenter: Dave
Agenda Item Type:
Time Requested (Minutes): 5
New Business
Attachments: Yes
BACKGROUND/EXPLANATION OFAGENDA ITEM:
The turntable winch assembly failed on our 1999 Digger Derrick Truck. The winch is not
repairable and needs to be replaced with a new assembly.
The truck is in the 2023 budget for replacement, however at this point delivery of a new
truck will likely be in 2024 -2025 so we will need to have our existing truck in working
condition until then and also for resale value.
Altec Truck Services will be doing the replacement of the turntable winch assembly along
with the annual inspection and dielectric testing for a total cost including tax of
$26,621.41.
attachment:
Altec Estimate
BOARD ACTION REQUESTED:
Approve winch replacement, inspeciton, and testing
Fiscal Impact: $26,621.41
Included in current budget: No Budget Change:
PROJECT SECTION:
Total Project Cost: Remaining Cost:
((0000000000/Y/0��
1 yrfr Service Estimate
1109 STAGECOACH RD
SHAKO PEE, M N, 55379-8042
us
Customer
Service Request
Estimate #
782107
Service Request # 15207806
Customer
HUTCHINSON UTILITIES COMMISSION
Unit Information
Account #
17193 1 Payment Terms NET 30
Customer Vehicle #
Contact
DAVE HUNSTAD
Model
D4060
Email
dhunstad@hutchinson.mn.us
Chassis VIN #
1HTSHAAR4YH270255
Phone
TFax
Mileage
Mobile
i
Unit Serial #
030OCK0152
Altec Representative
Assy Serial #(FA)
047-0023349
Contact
Michael J. Paschke
In -Service Date
09-Jun-2000
Email
mike.paschke@altec.com
Phone
I Fax
This Estimate Expires: 12-DEC-22
Notes:
Item
Description
Hours
Labor
Material
Expenses
Total
1
PM INSPECTION
- -
$990.00
$79.87
$0.00
$1,069.87
2
DIELECTRIC TEST
- -
$230.00
$0.00
$0.00
$230.00
3
REPLACE TURNTABLE WINCH ASSEMBLY
8.00
$1,160.00
$21,311.55
$0.00
$22,471.55
4
FREIGHT ESTIMATE
0.00
$0.00
$0.00
$1,050.00
$1,050.00
5
SUPPLIES AND ENVIRONMENTAL DISPOSAL FEES
0.00
$0.00
$0.00
$87.50
$87.50
Totals
8.00
$2,380.00
$21,391.42
$1,137.50
$24,908.92
*This estimate is provided with the understanding that items may be discovered during the repair process that may require additional labor
and/or materials to repair. Examples would include, but are not limited to, hidden damages or items that were not clearly visible or known
at the time of estimate, damaged internal components, fasteners and pins that may be rusted, seized or broken.
**This estimate does not include City, County, State or Federal taxes.
***Transportation or towing of the vehicle is not included in the estimate unless specified.
****Freight charges are estimated and may be adjusted to reflect the actual cost incurred on the invoice.
Please sign below to authorize this estimate
Printed Name:
P.O.
Date:
Signature:
Would you like to keep salvageable
parts removed from the unit?
Yes No
V1 10/13/22 Page 1 of 2
Altec Service Group Limited Warranty
Products rebuilt or repaired by Altec Service Group are warranted to be free from defects in material and workmanship at the
time of rebuild/repair subject to the following provisions:
§ Labor Coverage: For a period of six (6) months following the date of repair, no charge for labor shall be made for a repair or
replacement by the Altec Service Group.
§ Travel Coverage: For a period of thirty (30) days following the date of repair, no charge for travel shall be made for a repair or
replacement at the customers location by the Altec Service Group.
§ Parts Coverage: For a period of one (1) year following the date of repair, Altec will at its option, repair or replace any part
found to be defective in material or workmanship at the time of repair.
§ This warranty is limited to parts that are repaired or replaced by the Altec Service Group. Authorization and coverage of this
warranty will be at the discretion of the Altec Service Group.
§ Accessory items are excluded from this warranty and will be warranted from the original manufacturer.
This limited warranty is expressly in lieu of any other warranties, express or implied, including, but not limited to, any warranty of
merchantability or fitness for a particular purpose. Except as specified above, no associate, agent or representative of Altec is
authorized to extend any warranty on Altec's behalf. Remedies under this limited warranty are expressly limited to the provision
and installation of parts and labor, as specified above, and any claims for other loss or damages of any type (including, but not
limited to, loss from failure of the product to operate for any period of time, other economic or moral loss, or direct, immediate,
special, indirect, incidental or consequential damage) are expressly excluded.
Ser War 2-10 Altec Industries, Inc.
V1 10/13/22 Page 2 of 2
HUTCHINSON UTILITIES COMMISSION
Board Action Form
Agenda Item: Approval of Requisition 0009358 for Design of HCP Interconnect
Presenter: John Webster
Agenda Item Type:
Time Requested (Minutes):; 1
Attachments':
BACKGROUND/EXPLANATION OFAGENDA ITEM:
In order to transport natural gas directly to Heartland Corn Products (HCP) an
interconnect station must be designed, permitted and constructed. It is RCP's intention
to begin transporting natural gas on Hutchinson's pipeline as of October 1, 2023.
WSB will be performing:
Pipeline Engineering and Design
Mechanical and Electrical Engineering (Sub to LDIS)
Civil Surveying
Structural Design and Permitting
Civil and Roadway Design
Environmental Compliance
Natural Resource Desktop Review
Geotechnical, and
Construction Inspection
Work budgeted for in 2023. Due to extended lead times, HUC wishes to begin the
design and engineering work at this time to ensure station start-up prior to October 1,
2023.
All expenses incurred with engineering, design and construction of the HCP Interconnect
Station to be reimbursed by Heartland Corn Products to Hutchinson Utilities
BOARD ACTION REQUESTED:
Approval of Requisition 009358
Fiscal Impact: $269,248.60
Included in current budget:No Budget Change: No
PROJECT SECTION:
Total Project Cost: Est. $700,000 Remaining Cost: Est. $400,000
,.". HUTCHINSON
UTILITIES
xmawrw ,mission
WSB
701 XENIA AVE S SUITE 300
GOLDEN VALLEY, MN 55416
Note
Description:
PURCHASE REQUISITION
HUTCHINSON UTILITIES COMMISSION
225 MICHIGAN ST SE
HUTCHINSON, MN 55350
Phone:320-587-4746 Fax:320-587-4721
Date Requisition No.
10/18/2022 009358
Required by:
Requested by: JWebster
Item No. Part No. Description Qty Unit Due Date Unit Price Ext. Amount
WSB TO PROVIDE DESIGN, ENGINEERING
AND - INSPECTION OF THE PROPOSED
PIPELINE INTERCONNECT BETWEEN HUC
AND HEARTLAND CORN PRODUCTS (HCP).
SERVICES PROVIDED CONSIST OF:
PIPELINE ENGINEERING AND PERMITTING
MECHANICALAND ELECTRICAL
ENGINEERING (SUB TO LDIS)
PIPELINE HOT TAP DESIGN
CIVIL SURVEYING
STRUCTURAL DESIGN AND PERMITTING
CIVIL AND ROADWAY DESIGN
1 ENVIRONMENTAL COMPLIANCE 1.00 EA 08/14/2023 $269,248.600 $269,248.60
NATURAL RESOURCE DESKTOP REVIEW
GEOTECHNICAL, AND
CONSTRUCTION INSPECTION
PROJECT MUST BE COMPLETED PRIOR TO
OCTOBER 1, 2023.
WSB PROPOSAL: PIPELINE INTERCONNECT
2022A
THE PROPOSAL IS SUMMARIZED AS A TIME
AND MATERIAL, NOT TO EXCEED COST
ESTIMATE.
MFG. PART:
Total: 269,248.60
Date Printed: 10/21/2022 Requisitioned By: JWebster Page: 1/1
Pipeline Interconnect 2022A
FOR THE HUTCHINSON UTILITIES COMMISSION
a
6
October 20, 2022
John Webster, Director, Natural Gas Division
225 Michigan Street SE
Hutchinson, MN 55350
Re: Pipeline Interconnect 2022A
Dear Mr. Webster,
WSB is pleased to present this proposal to assist Hutchinson Utilities Commission (HUC) with the
design, engineering, and inspection of the proposed pipeline interconnect between HUC and
Heartland Corn Products (HCP) near Winthrop, MN.
This interconnect will provide natural gas to HCP for use at their ethanol plant. Services required
will include surveying, geotechnical, civil design, structural design, mechanical and electrical
engineering, pipeline hot tap design, permitting, and inspection. At this time, the project is
anticipated to be ready for service in the Fall of 2023. The project is anticipated to begin no later
than January 1st, 2023.
A detailed scope and cost breakdown is included in the following pages.
Once again, thank you for the opportunity to support Hutchinson Utilities Commission with their
pipeline projects. We look forward to the next steps.
Should you have any questions please do not hesitate to contact me at (865) 317-2545.
Sincerely,
Brandi P. Wolfe
Regulatory Compliance Manager
HUC—Interconnect 2022A_A
0
G�
1
WSB will provide the following services for the success of this project:
1. Pipeline Permitting & Engineering,
2. Mechanical and Electrical Engineering,
3. Surveying,
4. Structural Design & Permitting,
5. Civil and Road Design,
6. Environmental Compliance,
7. Natural Resources Desktop Reviews,
8. Geotechnical, and
9. Construction Inspection.
Details of each service and the associated assumptions:
I i J Flip' III < <;, ( l r,,, l l r1 t1J ,, g & D f g! t, e e r f ri g
The Pipeline Engineering team will handle the management of this project for the duration of plan. WSB
will design and coordinate the pipeline needed from the existing 12" transmission pipeline to the proposed
meter interconnect, through metering and filter skids, and ultimately to the custody transfer valve to HCP.
A hot tap will be designed and coordination with a hot tap company for installation is included. At this time
a final location for the site has not been determined. Two of the potential sites will require a road bore
design and road crossing permit. WSB has included line items for those tasks should they be required. If
a road bore is deemed unnecessary, that cost will be excluded.
Cathodic protection design is also included due to the high voltage electric lines in the immediate vicinity
of the hot tap and interconnect.
Procurement assistance for fabricated designs and contractors will be included.
Road access permitting will be included for the site entrance.
WSB will generate a job book for the interconnect to meet 49 CFR Part 192 documentation requirements.
At this time, a permit with MNPUC should not be needed for the interconnect.
El ,crk al t_w' 19I le I I g
The interconnect piping will include a meter skid, filter skid, and related equipment. Assumed natural gas
flow is 17,000 to 19,000 Dth/day. WSB's mechanical subcontractor LDIS will provide these services.
• Design duration estimated at 10 weeks, 11/15/2022—1/24/2023.
• Existing site drawings and models are available in native form provided by WSB.
• Site ambient and atmospheric conditions will be based on available data for Winthrop, MN.
• Site visits: no hours in estimate for site visit(s).
• All meetings will take place either electronically or in the LDIS office.
• One (1) hour weekly Client meeting have been included for the following disciplines as needed for
the duration of the project:
• Package Issues:
o IFR, IFA and IFC.
o If there is no separate IFB issue, will use IFC documents to bid.
• PHA is Excluded
• Construction / Startup:
o No hours in estimate for construction specifications.
HUC—Interconnect 2022A_A
o Minimal hours in estimate for construction RFI support via phone, total of 15 hours
between all disciplines.
o No hours in estimate for commissioning and startup.
• As-Builts:
o P&IDs with "minor red lines" from construction only items included.
Meter Skid 1 LDIS By WSB/HUC Design by LDIS
Mechanical,
Procurement, and
Project
Management will
be involved in
vendor coordination
meetings for
(assumed 10
weeks @ 2 hr/wk
each).
Filter 1 LDIS Y, by LDIS LDIS
Vendor data
Coalescer
needed to finalize
for IFC issue.
• Technical bid evaluations by LDIS includes up to three (3) bidders.
• 3 initial squad checks in estimate for technical vendor document and drawing reviews. Including
review of one (1) resubmittal to verify comments incorporated.
• No hours in estimate for vendor shop visits.
Process
• Process design basis included in scope.
• Process modelling based on client provided information for as a starting point for PSV checks,
hydraulics, COS, etc.
• Process Flow Diagrams (PFDs) excluded from scope.
• 3 P&IDs will have 3 revisions: IFR, IFA, and IFC.
• Sizing / Conditions of Service:
o Line Sizing
0 1 Filter
o Instruments
0 1 Meters
• Assumed no combustor for tank vents at this time but would recommend this to be reviewed
during design.
Mechanical
• Equipment and specialty items lists will be generated on LDIS standard templates.
• Specialty items will be requisitioned based on the specialty items list and manufacturer's catalog
datasheets.
• Datasheets / Specifications:
o Meter Skid
o Filter Coalescer
o Site Design Conditions
• Calculations:
HUC_Interconnect 2022A_A 3
o None
• Atmospheric storage tanks will be per API 12F, 13th edition.
• NACE material specification requirements and recommendations will be followed for compatibility
with customer supplied fluid compositional data. Some equipment will be exempt from NACE
material requirements (e.g. atmospheric tanks and other utilities equipment).
• No new specifications for paint, coatings and insulation will be generated.
• Formal pipe stress analysis and calculations will not be performed.
Piping
• Piping Guidelines:
o Will use the approved piping guidelines document for the basis of the piping design.
• Lists:
o Line List: will use the LDIS standard that imports into isometrics directly for only the items
desired to be shown on the isometric, all other items will be referenced in the line list for
fabrication.
• MTOs
o Technical evaluation of Piping MTOs will not be completed by LDIS.
o One 100% field/shop MTO only (i.e. no comparisons will be needed).
o No separate manual valve take -off, they will be included in the above MTO.
• Model Review Meetings: 60%
• Review of the physical design will happen by using Navis.
• Plans:
o 1 Plot Plan(s) — no piping or equipment arrangement drawings in estimate.
• Isometrics:
o 561SOs
o Will use latest LDIS template.
• Pipe Specifications:
o LDIS pipe specifications and valve datasheets will be used.
Civil/Structural
• Hours in estimate for the engineering/design of meter skid and filter platform structural steel only.
• No hours in estimate for the review of structural steel fabrication shop drawings.
• No hours in estimate for foundations. (WSB)
Instrumentation
• Lists:
o Instrument List (combination index and 10 list).
• Package Deliverables:
o Instrument Location Plans —on skid only — (1) Matchline
• IFB & IFP Instrumentation datasheets for:
o Coriolis Meter
o Temperature Transmitters
o Pressure Transmitters
o Differential Pressure Transmitter — filter skid
o Control Valve — skid over pressure control
• Cause & Effect Matrix, Control Philosophy, Programming, configuration not in LDIS scope.
Procurement
• Go out for quote on equipment and generate bid tab for both technical and commercial.
o WSB minimum number of bids required (3) and when sole sourcing is acceptable.
• Go out for quote on piping materials.
HUC—Interconnect 2022A A 4
irJ
o WSB/HUC minimum number of bids required (3) and when sole sourcing is acceptable.
• Go out for quote on instrumentation and generate bid tab for both technical and commercial.
o WSB/HUC minimum number of bids required (3) and when sole sourcing is acceptable.
• Create technical squad checks on vendor documents and drawings.
• Collect vendor documents and drawings and maintain the last revision.
• No Expediting or Job Book hours added
3,0 I
Includes two (2) days of survey team field work to establish topographic survey of the proposed
interconnect site at no more than 500 ft x 500 ft for potential construction disturbance. Office time is also
included for parcel search, base drawing, and 811 notification.
4 0 y, rTU live',,„d �f 11,,. -ge l,l f t✓:. F �„"'r. r", tlf f�
WSB's Structures Group (based in Golden Valley, MN) will complete structural plans and specifications
for one mechanical and one electrical building. The buildings will be designed per the latest edition of the
Minnesota Building Code and signed/certified by a Minnesota PE.
The structural group is making the following assumptions regarding the scope:
• Both buildings will be skidded Conex-style pre-fab structures with corrugated metal walls, lighting,
one man door with stoop, one window, and exterior wall access for utility penetrations included.
Building reactions will be provided by the manufacture.
o Instrumentation/Office building will be approximately 10' x 10' with insulation, HVAC, and
electrical outlets. Electrical penetration included.
o Meter/Mechanical building will be approximately 14' x 14'. Mechanical and electrical
penetrations included.
• No architect will be used for the buildings. If desired colors are required for walls and roof, owner
will need to specify for inclusion in our plans.
• Structures group to submit certified plans and specs to local agencies and obtain building
permits.
• Structural support during construction will address RFIs and shop drawing submittals, but
construction inspection will be completed by others.
The roadway design group will complete a grading plan and access plan for the chosen site.
The roadway group is making the following assumptions regarding the scope:
• Topographic survey will be complete by others
• Assumes the site will be approximately 150'xl50' at final grade
• The access road will connect to a Sibley County highway, it is assumed coordination with the
County will be completed by others (WSB Pipeline Permitting & Engineering)
• Drainage design and permitting will be completed by others (WSB Environmental)
• Geotechnical information and recommendations will be provided by others. (WSB Geotechnical)
• Turning movements will be reviewed
Owners and operators of construction activities disturbing one acre or more of land need to obtain a
National Pollutant Discharge Elimination System (NPDES) Construction Stormwater (CSW) Permit and
develop a Stormwater Pollution Prevention plan (SWPPP). The SWPPP is a plan to control sediment -
laden runoff and erosion prevention from the beginning of the project to end and may include post -
construction measures.
HUC Interconnect 2022A A
1R j
• SWPPP Development
o A certified Environmental Compliance Specialist will work with the project team to
develop the SWPPP narrative for the Hutchinson Utilities Improvement project. The
Environmental Compliance Specialist will have working knowledge of local and state
regulations to aid in the planning and development of accurate and complete SWPPP
narratives.
• Plan Set Review
o A certified Environmental Compliance Specialist will work with the project team and CAD
engineers to ensure that project plans are developed in accordance with good best -
management practices with consideration to applicable state standards and permit
requirements.
• MPCA Construction Stormwater Permit Application
o A certified Environmental Compliance Specialist will apply for the Hutchinson Utilities
Improvement project General Construction Permit through the Minnesota Pollution
Control Agency on behalf of the City of Hutchinson.
• Key Deliverables
o Original, signed and certified SWPPP narrative, detailed redlines of the project plan -set to
include necessary best management practices to meet permitting requirements, and
application to the MPCA for the project's Construction Stormwater General Permit.
7,0 'f .f / e 11
Task 1 — Level 1 (Desktop) Wetland Delineation and No -Loss
WSB will review the Sibley County Soil Survey, MnDNR Public Waters map, USFWS National Wetland
Inventory, FEMA flood zone map, U.S. Geological Survey (USGS) National Hydrography Dataset (NHD),
contours, and historic aerial photos for the project area. WSB will complete an offsite wetland hydrology
assessment to determine whether there are wetlands within the project area. WSB will prepare an
application for a No -loss Decision from the Local Government Unit (LGU) for the MN Wetland
Conservation Act, as applicable. Concurrence from the US Army Corps of Engineers (USACE) will also
be received.
Task 2 — Desktop Resource Database Search and Summary
WSB will use the following data sources to collect information needed for the Hutchinson Utilities Project:
• Minnesota Department of Natural Resources (MNDNR) Minnesota Conservation Explorer
(MCE) Natural Heritage Report
• U.S. Fish and Wildlife Service (USFWS) Information for Planning and Consultation (IPaC)
• Minnesota State Historic Preservation Office coordination
These database search reviews provide information regarding known sensitive resources that may be
near or within the project location. The information from these resources will be summarized in a
memorandum.
Natural Resources Services Assumptions:
WSB can proceed with the services within two weeks of receipt of authorization.
The process to obtain the wetland no -loss decision typically takes a couple of months.
Any application fees will be the responsibility of the Client.
The level 1 wetland delineation report includes time for 1 round of revisions per LGU / USACE
comments.
Site access permission will be granted.
If additional work is required beyond this scope, WSB will provide those services on a time and
materials basis following written approval from the Client.
HUC—Interconnect 2022A_A 6
• Utilization of ATV drill rig on grass surfacing
• GSOC utility clearance
• Drill rig mobilization
• Project Management
• Soil Classification, Lab Testing (moisture content and #200 wash), Boring Logs
• Geotechnical Report with recommendations for helical pile designs, fills, discussion of soil
properties and groundwater conditions.
N..
During the civil and mechanical construction of the interconnect, WSB is proposing to have one (1)
inspector provide construction oversight. Thorough documentation of the project will be provided with
daily inspection reports. A Certified Welding Inspector (CWI) will be available during pipeline installation
requiring welding.
Assumptions that construction would be performed for 3-weeks, with 50-hours of working time/per week
have been included. If construction differs from this estimate, the included regular- and overtime -hourly
rates will be used on a time -and -materials basis.
e a
The proposal is summarized as a Time & Materials (T&M), not -to -exceed (NTE) cost estimate. A detailed
breakdown is included as Exhibit 1.
1.0 Pipeline Permitting & Engineering
$59,092.00
tO Mechanical & Electrical Engineering (LDIS)
$132,030.60
3.0 Civil Surveying
$4,684.00
4.0 Structural Design & Permitting
$22,320.00
5.0 Civil & Roadway Design
$22,110.00
P.0 Environmental Compliance
$1,530.00
7.0 Natural Resources Desktop Review
$3,412.00
+�8.0 Geotechnical
$7,000.00
19.0 Construction Inspection
$17,070.00
HUC_Interconnect 2022A_A 7
1
DocuSign Envelope ID: 052DA2B8-86CF4CC9-B9E7-9FDF1303F5CB
5620 Ward Road Suite 200
4
OLMOISA
Arvada, CO 80002
Phone: 303-953-5333
Schedule of Service Rates for
Layout Design and Installation Services, LLC.
January I - December 31, 2022
The following rate schedule would be in effect for time and material work:
ErgiW Mana eme>Int
Project Manager I
$135.00/hour
Project Manager II
$145.00/hour
Project Manager III
$155.00/hour
Project Manager IV
$165.00/hour
Project Manager V
$175.00/hour
Project Engineer I
$130.00/hour
Project Engineer II
$140.00/hour
Project Engineer III
$150.000/hour
Project Engineer IV
$160.00/hour
Project Engineer V
$170.00/hour
PHA Scribe
$110.00/hour
PHA Facilitator
$165.00/hour
PHA Certified Facilitator
$185.00/hour
Enttineerinc Services (Process, Mechanical, Civil, Structural, Electrical, & Instrumentation)
Engineer I
$95.00/hour
Engineer II
$110.00/hour
Engineer III
$120.00/hour
Engineer IV
$130.000/hour
Engineer V
$145.00/hour
Engineer VI
$160.00/hour
Subject Matter Expert (SME)
$175.00/hour
Stress Engineer
$190.00/hour
Permitting Engineer
$220.00/hour
Desl n/MaI212in ervleeS (Piping, Civil, Structural, Mapping, Electrical & Instrumentation)
Drafter I $65.00/hour*
Drafter II
$70.00/hour*
Drafter III
$80.00/hour*
Designer/Mapper I
$90.00/hour*
Designer/Mapper II
$100.00/hour
Designer/Mapper III
$110.00/hour
Designer/Mapper IV
$120.00/hour
Designer/Mapper V
$130.00/hour
Designer/Mapper VI
$140.00/hour
Design Project Lead
$145.00/hour
DocuSign Envelope ID: 052DA2B8-86CF-4CC9-B9E7-9FDF1303F5CB
LDISJ
5620 Ward Road Suite 200
Arvada, CO 80002
Phone: 303-953-5333
Procurement Services
Procurement Specialist I
$85.00/hour
Procurement Specialist II
$95.00/hour
Procurement Specialist III
$110.00/hour
Procurement Manager
$125.00/hour
Proiect Sunnort Services
Project Planner/Scheduler I
$75.00/hour*
Project Planner/Scheduler II
$85.00/hour
Project Planner/Scheduler III
$95.00/hour
Project Planner/Scheduler IV
$105.00/hour
Project
Controller I
$85.00/hour
Project
Controller II
$95.00/hour
Project
Controller III
$110.00/hour
Project
Controller IV
$120.00/hour
Document Controller I
$70.00/hour*
Document Controller II
$80.00/hour
Document Controller III
$90.00/hour
Document Controller IV
$100.00/hour
Clerk/Admin/Assistant
$60.00/hour*
Records Coordinator I
$70.00/hour
Records Coordinator II
$80.00/hour
Field Services
Receiver/Controller
$100.00/hour* *
Field Engineer
$140.00/hour**
Field Manager
$140.00/hour* *
Construction Manager I
$145.00/hour* *
Construction Manager II
$160.00/hour* *
Laser Scanning Services
Per Site Basis
Other applicable charges, typical for most projects, are as follows:
• A 3.0 % surcharge for all labor amounts included on invoices to cover copies, plotter
use, supplies, computer use and maintenance, etc.
• Personal mileage will be reimbursed per the allowable IRS rate.
• Travel and other incidental expenses shall be reimbursed at cost.
* Non -Exempt positions subject to time and one half if dedicated to one project.
* * Field Services support subject to travel/per-diem costs in addition to T&M or negotiated rate
subject to WO.
Seconded employees will be negotiated based upon location and services rendered.